580,000 Recycled Tires Used to Prevent Landslide in Oregon

580,000 Recycled Tires Used to Prevent Landslide in Oregon - RaillyNews
580,000 Recycled Tires Used to Prevent Landslide in Oregon - RaillyNews

Project Background and Problem Addressed

In 1990, highway widening and elevation work on US 42 near Roseburg, Oregon, reactivated a dormant landslide beneath the roadway. Engineers identified that conventional soil fill would add excessive weight and further destabilize the slope. To reduce driving loads on the old slide mass while meeting roadway structural needs, contractors removed part of the heavy soil fill and replaced it with shredded scrap tires as a lightweight engineered fill. The removed soil served as a balancing counterweight lower on the slope.

Why Shredded Tires Were Chosen

Shredded tires provided a low-density alternative to soil, cutting imposed loads without sacrificing required volume. The material offered rapid placement with minimal compaction demands, good drainage characteristics compared with cohesive soils, and availability from regional suppliers. Cost incentives from Oregon’s DEQ recycling program reduced per-ton material costs, making the solution financially attractive compared with hauling lighter natural fill from distant borrowing sites.

Materials, Quantities, and Logistics

The project used approximately 5,800 short tons of shredded tire material—equivalent to roughly 580,000 individual passenger tires once processed into fragments. Four suppliers delivered material from distances ranging from 150 to 275 miles. Shipments used heavy trucks with about 28-ton payloads, meaning thousands of loaded trips. Contractors staged the shredded tires in lifts and placed them to design thickness, then covered the tire layer with compacted soil facing.

Design Details and Pavement Structure

At its thickest, the shredded-tire fill reached about 3.8 meters. Engineers capped the tire mass and shaped side slopes with 0.9-meter-thick compacted soil cover to protect against erosion, reduce frost effects, and provide a conventional working surface for pavement construction. The pavement section above the tire fill consisted of a 58-centimeter crushed-rock base and 20 centimeters of asphalt surfacing, designed to distribute traffic loads so the tire fill would compress predictably under service loads.

Construction Steps and Quality Controls

Contractors followed a step-by-step workflow: excavate and remove unstable soil; place shredded-tire material in defined lifts; lightly level and minimally compact each lift as specified; install soil cover layers and compact to required density; build the crushed-rock base; and lay the asphalt surfacing. Quality control included verifying source material gradation and contamination limits, monitoring lift thicknesses, field density checks on the soil cover and base, and instrumentation to record settlement and slope movement during and after construction.

Monitoring Results and Performance Data

Post-construction monitoring recorded approximately 50 centimeters of settlement in the tire fill—about 13% of its initial thickness—under the applied loads. Instruments such as inclinometers and extensometers showed that initial elastic deflections at the pavement surface were roughly twice those expected from equivalent conventional soil fills, but deformation rates stabilized over time. These observations indicate that shredded-tire fill can compress more initially yet reach a stable condition suitable for roadway applications when designed with appropriate pavement depth and settlement allowances.

Cost Breakdown and Recycling Incentives

Material costs normally run about $30 per ton, but Oregon’s DEQ recycled-material incentive covered $20 per ton, leaving a net material charge of close to $10 per ton. Including placement, spreading, and compaction, the project’s all-in cost worked out to about $18.33 per ton. Those incentives and the reduced need for hauling heavy native soil from borrow areas made the option cost-competitive for this site-specific landslide remediation.

Advantages, Limitations, and Lessons Learned

Advantages: shredded tires reduced mass and load on the slide, used diverted waste material, and lowered project costs through incentives and reduced hauling distances. Limitations: visible higher initial settlement and increased elastic deflection required deeper pavement structure and careful allowance in design. Lessons learned include rigorous source control for shredded material to avoid contaminants; designing for expected long-term settlement rather than only immediate deflection; and combining tire fill with a compacted soil cover to protect against surface erosion and facilitate pavement construction.

When to Consider Shredded-Tire Fill for Geotechnical Projects

Consider shredded-tire fill when the primary design objective is to reduce weight on unstable slopes, embankments over compressible foundation soils, or when conventional lightweight fills are unavailable or uneconomic. Perform site-specific settlement analyses, allow for greater initial compression, specify protective cover soils and robust pavement sections, and include a monitoring plan to validate predicted performance.

Practical Example Summary for Engineers

Project: US 42, near Roseburg, OR (1990–1993). Shredded-dash fill: ~5,800 short tons; maximum fill thickness: ~3.8 m; cover soil: 0.9 m compacted; pavement: 0.58 m crushed rock + 0.20 m asphalt; measured settlement: ~0.50 m (≈13%); incentive-reduced material cost: ~$10/ton net; all-in placed cost: ~$18.33/ton. These design and performance metrics give a practical reference for comparing lightweight fill alternatives on landslide remediation projects.

Key Takeaway

Using shredded tires enabled a cost-effective, waste-diverting, and technically viable remediation for a reactivated highway landslide in Oregon by significantly reducing imposed driving loads. Success required tailored structural design, allowances for extra initial compression, careful material controls, and instrumented monitoring to confirm long-term stability.

580,000 Recycled Tires Used to Prevent Landslide in Oregon - RaillyNews
AMERICA

580,000 Recycled Tires Used to Prevent Landslide in Oregon

Project Background and Problem Addressed In 1990, highway widening and elevation work on US 42 near Roseburg, Oregon, reactivated a dormant landslide beneath the roadway. Engineers identified that conventional soil fill would add excessive weight and further destabilize the slope. To reduce driving loads on the old slide mass while 🚄
Millions of Lego Pieces Lost at Sea in 1997 Still Washing Up on Beaches Today - RaillyNews
EUROPE

Millions of Lego Pieces Lost at Sea in 1997 Still Washing Up on Beaches Today

In 1997, a violent wave tore 62 containers from the deck of the container ship Tokio Express, releasing roughly 4.8 million small plastic toys into the North Atlantic. Decades later, hundreds of those toys—miniature life vests, snorkels, octopi, sharks, pirate sabers and green dragons—continue to appear on Cornwall’s beaches, carried 🚄
New Method Shortening Solar-Powered Water Disinfection Time - RaillyNews
AFRICA

New Method Shortening Solar-Powered Water Disinfection Time

A Nigerian study published in 2022 in Applied Water Science developed a reflective PET-bottle solar disinfection system that reduces E. coli inactivation time by two hours compared with conventional SODIS. The researchers built an array of eight transparent PET bottles positioned against a bespoke reflector that concentrates sunlight onto the 🚄
Demir Sabancı's $290 Million Skyscraper Move in Manhattan - RaillyNews
AMERICA

Demir Sabancı’s $290 Million Skyscraper Move in Manhattan

Project Acquired and Consolidated: Strategic Land Assembly Completed Sedesco, the New York arm of Demir Sabancı’s Sedes Holding, finalized a critical parcel consolidation on West 57th Street by purchasing the Schieffelin‑Bowne House for $42 million. This purchase brings Sedesco’s total land outlay in the block to roughly $290 million (about 🚄
Artificial Glacier Project in India to Combat Drought - RaillyNews
ASIA

Artificial Glacier Project in India to Combat Drought

Why Ladakh builds artificial ice towers and how they solve seasonal water shortages Engineers and community teams in Ladakh construct cone-shaped ice stupas to capture winter runoff and release it gradually during the spring crop season. They divert water from melt streams into a vertical injection system that sprays droplets 🚄
Luxembourg Accelerates Hiring of Foreign Workers Across 20 Occupation Groups - RaillyNews
EUROPE

Luxembourg Accelerates Hiring of Foreign Workers Across 20 Occupation Groups

High Pay Alone Doesn’t Close Luxembourg’s Skills Gap Luxembourg ranks first in the EU for average pay, yet employers report persistent shortages in qualified staff. Eurostat’s 2024 figures put the annual gross salary for full-time workers at roughly €83,000 (about €6,917 per month), yielding an estimated net monthly income near 🚄
The 400,000-Year Evolutionary Journey of Baikal Seals Revealed - RaillyNews
ASIA

The 400,000-Year Evolutionary Journey of Baikal Seals Revealed

Lake Baikal hosts a unique population of approximately 100,000 freshwater seals whose origin and persistence reveal a remarkable story of migration, isolation, and specialized adaptation. How did Baikal seals reach the lake? Genetic analyzes show Baikal seals (Pusa) sibirica) descended from a common ancestor with Arctic ringed seals roughly 400,000 🚄
Fatal Bear Attack in Canada Claims Lives of Mother and Daughter - RaillyNews
AMERICA

Fatal Bear Attack in Canada Claims Lives of Mother and Daughter

Multiple Bears May Have Been Involved, Officials Say Investigators located the second body after search teams coordinated by the Royal Canadian Mounted Police and provincial wildlife officers. British Columbia Conservation Service inspector Jeff Tire announced the recovery in a video update and said forensic and field evidence suggest more than 🚄

Be the first to comment

Leave a Reply