Turkey's Istanbul Airport which will provide access to the huge project, there was a flash developments about Gayrettepe Istanbul Airport Metro line.
Gayrettepe-Istanbul Airport metro contract, which was signed by ŞENBAY + KOLİN and 2016 € in 999.769.968,00, was taken over by CENGİZ + KALYON + KOLİN joint venture.
Istanbul 3 construction continues. Gayrettepe-YHL- which will be built to provide transportation from the city center to the airportHalkalı 1 of the metro line. stage.
M09.12.2016 Gayrettepe-Yeni Airport metro line, which was built on 11, is planned to carry 36 passengers in 70.000.
stations
1-Gayrettepe
2-Eyup
3-kemerburgaz
4-Gokturk
5-İhsaniye
6-New Airport
When the line is completed; It will be integrated with Yenikapı-Haciosman metro line and metrobus operation at Gayrettepe station.
GAYRETTEPE ISTANBUL AIRPORT METRO STATIONS CAN BE SEEN ON INTERACTIVE MAP