Studies on Turkey's longest railway tunnel will accelerate

Turkey's longest railway tunnel will accelerate work in: Turkey's longest railway tunnel project is anticipated to be in the double-tube studies were accelerated.
Gaziantep and Osmaniye Garden Nurdağı will connect the towns and 10 200 thousand meters in length with Turkey's longest railway tunnel work is in progress on the project, which will double the tunnel digging machine.
20 THOUSAND BIN 400 METER TUNNEL
TCDD Road Agency chairman Selahattin Sivrikaya, said in a statement on the construction site, the Republic of Turkey State Railways (TCDD) by the Adana-Gaziantep-Malatya conventional line on the garden-Nurdağı total 8 meters in diameter for double tube tunnel built between the county 20 thousand 400 meter tunnel reminded the excavated .
STUDIES WILL BE COMPLETED IN 2 YEAR
Work is scheduled to be completed within the year 2 transfers Sivrikaya, the completion of the tunnel of the existing railway line will be shortened 17 mileage. Sivrikaya, the project within the scope of the project so far progressed by classical excavation, stating that the most preferred method in the world around the tunnel digging machine will be used, said it will accelerate the work even more.
193.2 MILLION WILL BE A COST
The project is expected to cost 193 million 253 thousand pounds, with more than 20 technical personnel working with 200.