Renovation of Erzurum Airport

erzurum airport track renovation work begins
erzurum airport track renovation work begins

The renovation of the Erzurum Airport track was initiated. Within the scope of the studies, conversion of 08L runway head to CAT III standards will be completed.

The project will include 4 cm excavation and 19 cm asphalt pavement for the concrete pavement and surface peeling of the existing runway and will cost 24.745.000,00 TL. It is reported that all necessary measures have been taken to ensure that the work planned to be completed on 09.02.2020 does not adversely affect air traffic.