Delayed and never started lines according to the Istanbul rail system investment program



Delayed and never started lines according to the Istanbul rail system investment program
Delayed Lines by Rail System Investment Program: 57.46 km

Kadikoy-Kartal: (21.66 km) 2011 will be finished. It's not over in time.

Bagcilar-Olympic: (15.8 km) 2012 would end in the middle. Still waiting for the opening.

Üsküdar-Çekmeköy: (20 km) 2013 is planned to be finished.

According to the Rail System Investment Program Lines that Never Start: 51,5 km.

Ataşehir-Monoray: (11 km). 2012, and 2013 will be finished. Why didn't it start.

Besiktas-Giyimkent-Bağcılar: (24.5 km) 2012 began in the middle, and will end at the beginning of the 2015.

Bakirkoy-Beylikdiuzu (25 km) 2013 start and 2015 also finished.

Bakirkoy-Bagcilar: (9 km). He would start at the beginning of 2013 and finish at 2014.

Yenikapı Bakırköy: (7 km) 2013 should start at the beginning. Because it's planned to end at 2015.

Ünalan-Mecidiyeköy (11,8 km) planned to be built between 2014 UM 2015. No work involved in planning.

High Speed ​​Train News



Railway Tenders of the Week

20 / 05 / 2019 for events week

This Week Navigation

loading Events
Sat 25
No Events Found
Sun 26
No Events Found

Free Email Subscription

your email adress:

Be the first to comment

Yorumlar

This site uses Akismet to reduce spam. Learn how your comment is processed.