Adif has opened a design tender worth an estimated €4.67 million (excluding VAT) to adapt the Madrid–Basque Country rail corridor so it can carry road semi-trailers on specially designed freight wagons. The contract aims to modify infrastructure along a 528 km electrified route between Azuqueca and Júnidiz, enabling efficient intermodal shifts and strengthening links with the Atlantic Corridor and key logistics hubs.
29 Tunnels and 37 Critical Points Targeted for Modification
Detailed route inspections identified 37 intervention points: 29 tunnels, four overpasses and four small structures. For tunnels, engineers plan to lower the track bed by up to one meter where required to achieve the necessary loading gauge for semi-trailers. Overpasses marked for intervention will receive structural renewal or profile adjustments so vertical clearances meet the new operational envelope. Work on small structures focuses on drainage and platform edges to remove local pinch points.
Procurement Timeline and Contract Phasing
The tender was published on 25 November with bids due by 26 January 2027 and a bid opening scheduled for 9 March 2027. The awarded design contract spans 36 months and is split into two phases: a 24-month first phase and a 12-month second phase. This staged approach lets designers produce preliminary and detailed designs, then update final construction documents after field verification and stakeholder review. The project is eligible for co-financing from European Union funds, allowing Adif to combine national budgets with EU grants to accelerate delivery.
Operational Plan: 18 Weekly Freight Trains in First Stage
The initial service concept foresees 18 weekly freight trains—nine in each direction—operating along the corridor once infrastructure adaptations are complete. Trains will run between inland logistics hubs such as Azuqueca and Valladolid and the Júnidiz terminal near Vitoria-Gasteiz, improving capacity for long semi-trailer movements. Scheduling nine weekly departures per direction allows operators to offer predictable slots for shippers, concentrate wagon pools for higher utilization, and synchronized feeder road connections at both ends.
Terminal Capacity and Modal Shift Impact
At Júnidiz, planned terminal upgrades aim to raise annual handling capacity to 60,000 units. That increase derives from adding more sidings for loading/unloading, installing faster cranage or roll-on/roll-off systems depending on chosen wagon technology, and streamlining yard flows with digital gate and appointment systems. Projected benefits include reducing long-haul truck kilometers, lowering road congestion on the Atlantic corridor, and cutting greenhouse gas and particulate emissions by shifting high-tonnage flows to electric traction.
Engineering Measures: How to Fit Semi-trailers on Existing Lines
Adapting conventional rail infrastructure to carry semi-trailers requires a combination of geometric, structural and operational measures. Geometric work includes lowering ballast and track to increase vertical clearance, re-profiling tunnel linings where ballast lowering is insufficient, and modifying overhead line equipment to maintain electrical safety clearances. Structural measures include strengthening bridge decks or replacing low parapets with slimmer profiles. Operational changes involve defining maximum dimensions for loaded trailers, new shunting procedures at terminals to expedite loading, and updated maintenance regimes to monitor track settlement after lowering.
Examples and Comparative Investments
Adif’s project follows adaptations already underway on other Spanish corridors such as Madrid–Zaragoza and Zaragoza–Lleida–Tarragona, where investments exceeding €330 million focus on tunnel and overpass works to accommodate semi-trailers. Those projects illustrate typical unit costs: tunnel re-profiling and track lowering are capital-intensive but offer long-term modal shift gains. Lessons from those corridors—staging construction to keep traffic running, using temporary speed limits during works, and scheduling ballast relocation during low-traffic windows—inform the Madrid–Basque Country plan.
Practical Steps for Designers and Contractors
Design teams responding to the tender should plan a stepwise delivery: 1) immediate field surveys and laser scanning of tunnel profiles; 2) soil and geotechnical investigations where track lowering is proposed; 3) preliminary clearance studies to identify where ballast lowering alone suffices versus where lining re-profiling is needed; 4) structural assessments of overpasses and bridges; 5) safety and electrical interface studies for overhead lines; and 6) preparation of phased implementation drawings that allow railway operations to continue with minimal disruption. Including risk registers and contingency design options for archaeology, unexpected utilities or groundwater is essential.
Network Strategy: Scaling a Road-Rail Highway Across Spain
Adif is expanding a network of road-rail corridors across Spain to promote longer-haul freight transfer to rail. Work on more than 20 routes—coupled with terminal upgrades and targeted investments—seeks to create a mesh of high-capacity links connecting inland distribution centers with maritime gateways and cross-border corridors into France. Scaling this model requires coordinated timetabling between operators, investment in wagon fleets suited to semi-trailers, and commercial agreements that guarantee regular train paths for shippers.
Expected Outcomes and Measurable Benefits
When implemented, the project should increase capacity for intermodal semi-trailer flows, reduce truck traffic on key corridors, and accelerate freight’s shift to electrified rail. Measurable indicators to track success include weekly train departures served, terminal throughput (annual units handled), average wagon utilization, truck-km avoided, and CO2-equivalent emissions reduced per year. Clear baseline data before works and an agreed monitoring framework will let Adif and funders quantify benefits during phased rollout.
Key Dates and Next Steps for Stakeholders
Stakeholders—design firms, contractors, terminal operators and logistics customers—should note the bid deadline of 26 January 2027 and plan resources for a detailed proposal that includes fieldwork schedules and a phased design methodology. After contract award, early coordination workshops with train operators and terminal managers will finalize operational requirements and allow the design to reflect practical loading/unloading workflows. Prompt procurement of specialized wagon fleets and terminal handling equipment will be critical to start commercial operations as infrastructure milestones are achieved.