Budget Increase and Board Review
LA Metro officials propose a $296 million increase to the D Line Extension Phase 2 budget, raising the total to $2.87 billion for the roughly 4.17-kilometer segment between Beverly Hills and Century City. The funding change is scheduled for consideration by the Metro board on December 3, 2026. The proposal focuses on closing immediate funding gaps tied to contractor claims, extended schedules, and final roadway restoration costs.
Breakdown: Where the $296 Million Will Go
Officials allocate the additional funds into two primary buckets: $151 million for negotiated delay claims with the Tutor Perini/O&G joint venture and $145 million for remaining construction activities, schedule-driven costs, and final site restorations. The recommended total excludes an estimated $88.7 million in financing costs, which remains separate from the construction contingency. This split clarifies that roughly half the increase addresses claims while the remainder covers tangible completion needs.
Revised Opening Date and Operational Plan
Phase 2 reached approximately 95% physical completion by September 2026, but Metro now targets revenue service to begin in fall 2027 rather than spring 2027. The updated schedule allows for system testing, integrated signal and traction systems validation, final roadway and pedestrian training restorations, and coordinated staff training. Hyundai Rotem’s HR5000 fleet will supply rolling stock for the segment; Metro expects 20 HR5000 cars to operate on Phase 2 when it opens.
Technical Issues Driving Cost Growth
Several site-specific technical requirements increased scope and cost: improved seismic tunnel linings to meet updated resilience standards; unanticipated drainage and excavation complexity at the Century City station; redesign and reconfiguration of a station entrance to meet access and urban design constraints; and additional geotechnical mitigation measures discovered during deep excavation. Each of these items required design revisions, extra materials, and extended contractor work windows, which together contributed materially to the budget uplift.
How Delay Claims Were Negotiated
Metro negotiated delay-related compensation with the Tutor Perini/O&G joint venture rather than pursuing protracted litigation. The negotiation considered construction logs, documented change orders, differing site conditions, and schedule analyses. Metro staff evaluated contractor-submitted time impact analyzes and cost substantiation to arrive at a negotiated settlement of approximately $151 million, balancing risk transfer and schedule certainty to expedite completion.
Financing Strategy and Measure R Role
Metro staff recommend covering the additional appropriation from Measure R transportation capital funds. If approved by the board, the Phase 2 budget would exceed its original 2017 baseline by ~17.6%, reflecting both inflationary pressures and scope evolution. Using Measure R preserves flexibility in other capital accounts but reduces the programmatic cushion available across the regional capital portfolio.
Implications for Phase 3 and Regional Service Plans
Phase 3, which extends service between Century City and Westwood, remains on track for a 2027 opening under Metro’s published sequence, though calendar slippages on Phase 2 could force coordination adjustments for commissioning crews and trainsets. Metro will need to align rolling stock deliveries, operator training, and system integration windows across phases to avoid cascading schedule impacts.
What Riders and Local Stakeholders Should Expect
Residents and businesses along the corridor should expect final roadway restoration work and increased testing activity through mid-2027. Metro plans staged public communications to announce testing milestones and the formal opening date before final commissioning is complete. Nearby pedestrian and traffic detours tied to finishing touches will be localized and scheduled to minimize peak-hour disruption where possible.
Data Points and Examples Illustrating the Change
Concrete examples underpinning the increase include: additional waterproofing and thicker tunnel liners required after geotechnical re-evaluation (cost drivers: materials and specialized labor), extended dewatering and excavation support at Century City station (cost drivers: prime contractor schedule and subcontractor overtime), and reconfigured station entrances to meet accessibility and design commitments (cost drivers: rework and coordination with adjacent utilities). Together, these items demonstrate how design evolution during late-stage construction commonly yields concentrated cost growth.
Next Steps for the Board and Public
Metro staff will present the full request package and supporting documentation at the December 3, 2026 board meeting. The board will evaluate the negotiated settlement terms, the proposed draw from Measure R funds, schedule mitigation plans, and risk-reduction measures for remaining works. If the board approves the appropriation, Metro will finalize contractor change orders and proceed with targeted completion milestones to meet the revised fall 2027 revenue-start objective.