Infrastructure Problem Solved in Istanbul

Infrastructure Problem Solved in Istanbul
Infrastructure Problem Solved in Istanbul

Üsküdar, where the most floods are seen, with more than 2019 billion TL investment in Istanbul since 11, KadıköyThe chronic flooding problem was resolved at 85 points, including the districts of Kartal, Beyoğlu, Sarıyer, Beşiktaş, Avcılar, Büyükçekmece, Küçükçekmece, Zeytinburnu and Fatih.

YEŞİLKOY NEIGHBORHOOD

In Yeşilköy District, the lines were operating with a mixed system, and because the channel cuts were insufficient, floods were experienced. The production of 6 thousand 712 meters of rain water and 6 thousand 772 meters of waste water line in Yeşilköy was completed in July 2021.

TANTAVI TUNNEL AND PRAISE UNDERPASS

In rainy weather, floods were experienced in Namazgah Underpass and Şile Highway Tantavi Tunnel. İSKİ solved the raid problem in October 100 by constructing a thousand 856 meters of waste water line and a thousand 2021 meters of rain water lines.

BÜYÜKÇEKMECE SERİNPINAR AVENUE

Work has been completed on Büyükçekmece Serinpınar Street, which is flooded in rainy weather. 400 meters of stream improvement, 200 meters of rain water line and 3 thousand 200 meters of waste water line were manufactured on the street.

ÇEKMEKÖY SERİNERE

Due to the inadequacy of the wastewater lines in Çekmeköy Serindere, the wastewater was mixing with the stream and flowing into the Elmalı Drinking Water Basin. There were floods due to the untreated creek. 2 thousand 400 meters of creek rehabilitation, 4 thousand 370 meters of waste water production was done. Studies continue.

BEŞİKTAŞ AKMERKEZ LEVAZIM Stream reclamation

The existing sections in Beşiktaş Akmerkez Levazım Creek were insufficient. 440 meters of stream was rehabilitated. 253 meters of waste water line and 133 meters of rain water line were built. The works have been completed.

BEŞİKTAŞ DISTRICT BARBAROS SQUARE

Since there was no rain water line in and around Beşiktaş Barbaros Square, floods were experienced after every rain. 945 meters of rain water channel was built in the region. The works were completed in July 2021.

BAYRAMPASA MANASTIR AVENUE

There were floods in Bayrampaşa Manastır Caddesi due to the lack of sections. 222 meters of rain water and 382 meters of waste water line were manufactured on the street. Work was completed in February 2021.

THE STREETS OF NUZHETİYE AND POET NEDIM

There were floods in Beşiktaş Nüzhetiye and Şair Nedim Streets due to insufficient canal sections. 976 meters of rain water and 750 meters of waste water line were produced in the region. Work was completed in March 2021.

UMRANİYE KÜÇÜKSU AVENUE AND AFFILIATED STREETS

There were floods in Ümraniye Küçüksu Street during heavy rains. Waste water lines were operating with a mixed system. 810 meters of rain water and 730 meters of waste water line were built on the street. Work was completed in February 2021.

MECLİS-İ MEBUSAN AVENUE

After the rain, floods were experienced in Beşiktaş Parliament-i Mebusan Street. Work with the 750-meter rainwater line and waste water line manufacturing was completed in September 2020.

BAKIRKOY KENNDY AVENUE

Bakırköy Kennedy Caddesi had lines operating with a mixed system and existing sections were insufficient. A thousand 430 meters of waste water line and 550 meters of rain water line were manufactured on the street. Work was completed in July 2020.

BAKIRKOY KARABAL Stream

The existing sections in Bakırköy Karabal Stream were also insufficient. A thousand 230 meters of box culvert creek rehabilitation, 680 meters of waste water line and 122 meters of rain water line were manufactured in the creek. The works are in progress.

BAKIRKOY INCIRLI AVENUE AND GENERAL ŞÜKRÜ KANATLI AVENUE

Bakırköy İncirli, General Şükrü Kanatlı Caddesi and Filiz Sokak had lines operating with a mixed system and the existing sections were insufficient. 2 thousand 846 meters of waste water line and 270 meters of rain water line were manufactured on the street. works have been completed.

BAKIRKOY YEŞİLYURT NEIGHBORHOOD VARIOUS STREETS AND STREETS

Many streets and avenues in Yeşilköy District did not have rain water lines. There were floods because the canal sections were insufficient in the places where it was located. 3 thousand 950 meters of rain water and 832 meters of waste water lines were manufactured. Work was completed in October 2021.

KADIKÖY

KadıköyRainwater and wastewater problems have been experienced for many years in the central points of . Waste water into the Marmara Sea due to mixed lines, Kadıköy Rainwater was entering the Treatment Plant. 482 meters of stream improvement, 820 meters of rain water line and 3 meters of waste water line were manufactured. Work was completed in September 620.

EMİNÖNÜ UNDERpass

There were two pedestrian underpasses in front of Eminönü Yeni Mosque and Spice Bazaar. Existing pumps in the underpasses were renewed and their capacity was increased. A pump station was manufactured, with one main and one back-up for each of the two pedestrian underpasses.

ÜSKÜDAR

After every rain in Üsküdar, floods occurred in and around Üsküdar Square. 822 meters long Çavuşdere Stormwater Tunnel, 906 meters long Bülbüldere Stormwater Tunnel, rainwater collector, waste water collector and network line were built in the region. Work was completed in September 2021.

ZEYTINBURNU

Sections in Zeytinburnu were insufficient, the stream was working with a mixed system. A thousand 250 meters of stream, 260 meters of rain water, 2 thousand 600 meters of waste water line were manufactured. The works are in progress.

EAGLE

After heavy rains, floods occurred in Kartal, sections and lines were insufficient. Work was carried out in Neyzen Tevfik Square, Savarona Square, Kartalbaba Underpass, Kartal Square and Soğanlık Street. 2 thousand 70 meters of waste water line, 2 thousand 26 meters of rain water line, 702 meters of stream improvement were manufactured. The works were completed in July 2021.

BÜYÜKÇEKMECE ALBATROS

Waste water and rain water lines had to be separated in Büyükçekmece Fatih and Pınartepe Neighborhoods. Waste water entry into the sea was stopped at 15 points. 4 thousand 976 meters of waste water channel, 2 thousand 740 meters of rain water channel were built. Work was completed in December 2021.

MECIDIYEKOY

There were floods on Şişli Büyükdere Street and its close vicinity due to the insufficient cross-section rain water line. 15 meters of waste water line and 176 meters of rain water line were built in the region. Work was completed in December 2020.

ORTAKOY

There were raids in and around Beşiktaş Ortaköy Square during heavy rains. 3 thousand 337 meters of stream rehabilitation and 183 meters of waste water line were made in Beşiktaş.

IN THE CABINET

The lines in Dolapderede were working with a mixed system. 2 thousand 500 meters of waste water and a thousand meters of rain water lines were manufactured. The works were completed in August 2020.

BEYKOZ

There was no waste water line in Barış Manço and Körfez Avenues. The old lines on Kelle İbrahim Street were operating with a mixed system, and the Beykoz Stream on Süreyya İlmen Street was dangerous for vehicle crossings as the road crossing was deformed. A 17-meter-long steel bridge, 450-meter-long waste water line and 15-meter-long rainwater line were built in the region.

USKUDAR LIBADIYE AVENUE AND AFFILIATED STREETS

There were floods during heavy rains in Üsküdar Libadiye Street. Small diameter lines were enlarged, new lines were allocated in the parts where there was no rain water line. A 684-meter-long rainwater line and a 875-meter-long waste water line were constructed. Work was completed in February 2021.

UNKAPANI BRIDGE

There is a solution to the floods experienced in rainy weather on Fatih Vatan Street, Aksaray Square, Unkapanı Underpass and Namık Kemal Street. A 510-meter-long rainwater tunnel will be built between Unkapanı Bridge and Aksaray Square. The production of the 700-meter section has been completed. Work continues on the 810-meter section.

MALTEPE YALI NEIGHBORHOOD

In the Yalı District of Maltepe, there were floods in the area where the Yalı Stream and Cemalbey Streams are located. Martyr Nedim Özpolat in the region, Marshal Fevzi lighter, Dr. 964 meters of stream improvement, 243 meters of storm water line and 466 meters of waste water line were built on Sadik Ahmet Boulevard and the streets around it. The works were completed in May 2021.

In many points in Istanbul, the infrastructure problem has been solved. The works continue unabated.