The Turkish Republic State Railways (TCDD) previously cancelled Kurtalan-Siirt Railway Construction Project The project, which was published in the Public Procurement Bulletin on April 24, 2025 and cancelled on May 14, 2025, was reopened to tender after the revisions.
Tender Cancellation and Reasons
The first tender was cancelled on May 14, 2025, with an announcement published on the Public Procurement Agency's website. The reason for the cancellation was the changes that needed to be made to the tender documents. TCDD announced the tender again after completing the necessary arrangements.
New Tender Date and Place
According to the statement, the new tender Tuesday, June 17, 2025 at 11:30 It will be held in the TCDD General Directorate Purchasing and Stock Control Department Meeting Hall (Ground Floor, Room No. 1015).
Project Details
Within the scope of the Kurtalan-Siirt Railway Project, 61 kilometers of new railway line will be built. The project also includes:
- 3 station buildings
- 6 main tunnels
- 12 escape tunnels
- 2 viaducts
- There will be 3 cut-and-cover tunnels.
The project will start from the site delivery To be completed within 1800 calendar days Targeted.
Regional Impacts of the Project
With the implementation of the Kurtalan-Siirt Railway line, it is expected that the transportation infrastructure in the region will be strengthened and economic activity will increase. This project is considered an important step that will improve the travel opportunities of the people of the region and contribute to the development of trade.