Halkalı The Opening Date of Istanbul Airport Metro Line Has Been Announced

Halkali istanbul airport metro line is put into service at the end of the year
Halkali istanbul airport metro line is put into service at the end of the year

Minister of Transport and Infrastructure Adil Karaismailoğlu Halkalı-Istanbul Airport Metro Line made examinations at the central construction site. Press releases Karaismailoğlu that the project would be completed when the hour drew attention to the speed of 120 kilometers with a capacity of Turkey's fastest subway. Karaismailoğlu, “Halkalı- We will complete the Istanbul Airport Metro at the end of 2022 and put it into service of Istanbul residents ”.

"Both the east and west sides of Istanbul will reach our new Istanbul Airport by metro line"

With Istanbul Airport Halkalı'When the subway line, which will connect y completed per hour speed of 120 kilometers with a capacity of Turkey's fastest subway would be stating the Minister Karaismailoğlu, "When we started the construction in 2018 of 31,5 kilometers of our line, the average of 600 thousand passengers a day we opened HalkalıWe will be able to transport to the airport quickly, comfortably and safely. A citizen of ours boarding from Gebze Halkalıafter reaching Halkalı-It will complete this ring with the Airport and Airport-Kağıthane-Gayrettepe line. "

"7 station Halkalı-Our Airport Metro is also integrated with Gayrettepe-Airport Metro, and with Gayrettepe. Halkalı will make uninterrupted transportation possible between. "Transportation to our new Istanbul Airport from both the east and west sides of Istanbul to one of the largest airports in the world will be provided by the metro line". Karaismailoğlu, Halkalı- He said that the Istanbul Airport Metro will be completed at the end of 2022 and put into service for Istanbul residents.

"With the completion of the project, access to other metro lines will be provided"

Minister Karaismailoğlu said that with the completion of the project, access to metro lines that surround Istanbul like a network will be provided. Karaismailoğlu, “Halkalı station to Marmaray line and Yenikapı-Kirazlı-Halkalı line, from Olimpiyatköy station, to Olimpiyatköy-İkitelli line, from Kayaşehir Station, to the Başakşehir-Kayaşehir metro line reaching Çam and Sakura City Hospitals whose construction is undertaken by our ministry, and from Fenertepe Station to the Vezneciler-Sultangazi metro line.

Shared the details of the project

Sharing the details of the project, Minister Karaismailoğlu continued as follows: “Approximately 3 thousand people worked on the subway line. We made 9% progress by digging over 33.2 kilometers with the Tunnel Drilling Technique. In NATM tunnel work; We made 3.8% progress by excavating over 24.5 kilometers. In addition, we reached a rate of 7% in the construction of 1 subways, 10 high-speed train station and 24.7 scissors-like stations. Reinforced concrete structures and finishing works; We completed 63%. In our metro works, NATM tunnel construction continues on warehouse connection lines.

"We are always with and near Istanbul and Istanbulites"

“With Istanbul Airport, we embroider the interior of the city with metro and rail systems, just as we made this metropolis a hub for the world. We implemented the transportation reform in Istanbul, we eased the traffic frustration with our brave projects. "