AK Party Central Disciplinary Board Chairman and Adıyaman Deputy Ahmet Aydın announced that the drilling work has started in Gölbaşı Adıyaman Kahta High Speed ​​Train Survey Project.


Ahmet Aydın stated that the teams started to work on his official twitter account and said, “Between 39 + 240 68 + 000, it is aimed to drill a total of 20 meters with 3 machines between Yenigüven (Adıyaman exit) 4.515 kilometers after the exit of Besni. "There are 5 tunnels, 5 bridges, 7 underpasses, and 3 overpasses in this range."

 