Platform and Signalization Work Begins Again in 42 Houses in Izmit

The platform and signalization studies are starting again in Izmit houses.
The platform and signalization studies are starting again in Izmit houses.

New stops are being made in place of the old 42 stops in the 2 Evler area on the new line to be used by the suburban train between Arifiye and Pendik. Studies that have been interrupted for about 10 days are expected to start again.

According to the news of Muharrem Şenol from Özgürkocaeli; The construction of electricity and signaling lines, called the new platform and catenary, has been ongoing for a long time in the Izmit 42 Evler region. Adapazarı Arifiye-Izmit-Pendik suburban train line, which was stopped due to the High Speed ​​Train operation in 2012 and reopened on a single line after 3 years, was added to the number of two. Work on the second line is still continuing in the Izmit 2015 Evler area.

COMPANY CALLED

Platform and electrical signaling works were carried out in the area where the rails were laid. However, due to the disagreement between the contractor firm and TCDD, the work has been suspended for 10 days. It is stated that the TCCD has re-agreed with the company and the construction of the work will start again soon. The works expected to be completed in August may also sag a little more.

CALENDAR WILL SHAKE

While the infrastructure work of the two platforms is continuing, there is currently no work on the lines. Infrastructure of platforms is completed. In the superstructure, the production of platforms was started. Work in the area started on 20 February. The construction of the platform with 20 people was expected to be completed in August, but after the developments, the calendar seems to be slightly sagging.