In Russia, a new one has been added to the big works that Turkish construction companies will sign. The first pickaxe is hit for the construction project, which has been working on it for a long time, about half a billion dollars. The Turkish company Limak will officially start a 2017 billion-rubles highway construction project in the Republic of the Russian Federation of Bashkortostan (Bashkortostan), with which it signed its first agreement in 33,5 with its partner Marashstroy.

Ufa Eastern Output will start the projects defined as Highway Construction, Radiy Başkortis President of the Republic of Turkey Ambassador to Moscow with Mehmet Habirov Samsara was announced during a meeting on Thursday in the capital Ufa.

Limak and Marashstroy's joint company “Limakmaraşavtodarogi”, the construction of the “Ufa East exit”, a transportation corridor project of 5 billion rubles, including tunnels between M7 and M33.5 highways, which President Habirov calls 'one of the biggest Bashkort-Turkish joint projects in history'. said he would make it happen.

Habirov announced that the first advance payment of $ 26 million was made to the contractor company and construction will begin on Monday through tunnel works.

Başort leader stated that there are other big projects on the agenda and negotiations with other Turkish companies are continuing.

Limak Construction and its project partner in Russia, Marashstroy, signed the “Ufa East Exit Road” project on July 27, 2017. The statement made at that time included the following information:

“The project, where the build-operate-transfer model will be implemented, is carried out on behalf of the Russian Federation under the Concession Agreement between the Republic of Bashkir and the Concession Owner Bashkir Concession Company (BCC). Limak will take an active role in the privileged BCC company for 25 years in partnership with the Russian company VTB Capital for XNUMX years.

There are tunnel, bridge, viaduct and embankment road sections on the route of approximately 12.5 kilometers. The project is foreseen to reach a capacity of 22 thousand 700 vehicles per day. ”

When signatures were signed in 2017, the following news on the subject was reflected in the media:

“Limak, which is a partner of the Bashkir Concession Company (BCC) company established for this project with the Russian company VTB Capital, will also undertake the contracting of the business.
The construction of the highway is expected to take 4 years, while the operation period will be 25 years.

The 12.5 km highway project will consist of 2 lanes, 2 departures and 4 arrivals. The project includes a 1,250-meter tunnel and bridges and viaducts with a total length of 2,600 meters.

The road, which will have a capacity of 22,700 vehicles / day, will connect the city of Ufa to the bus from the east.

Limak will carry out the construction of the road together with the company Maraşstroy, of which it is already a partner at Rostov Airport in Russia.

Commenting on the subject, Limak Holding Board Member Serdar Bacaksız said, “We will complete this project in 4 years. The project is a very interesting project in terms of engineering.

There are both a long tunnel and 2,600 meters long bridges and viaducts on the highway route. At the same time, it is the biggest work to be done by Turkish contracting companies after the improvement of relations with Russia.

We believe that the investment and operation of this project to our company will strengthen the relations between the two countries. As Limak, we are a company that aims to be permanent in the geographies we visit. This investment is an indication that we are permanent in Russia in the long term in terms of being a public-private investment project ”. said."