Varsak Bus Terminal Will Carry Passengers in August

bus station will carry passengers in August
bus station will carry passengers in August

Antalya Metropolitan Municipality, 3. Stage Rail System Varsak-Otogar Line sandbag test drives started. After the completion of the safety tests, it is planned to start passenger flights on the Varsak-Otogar line.

3, which was opened before the tests were completed and then the flights were stopped. Stage Rail System Varsak Bus Station has been completed to a large extent test work to eliminate deficiencies. As part of the safety tests, the test drive was started with sandbags before the tram started to carry passengers. Following the successful completion of the tests, the tram is expected to begin carrying passengers in August.

WAGONS CARRY SAND BAGS
Antalya Metropolitan Municipality Mayor in the 3rd Stage Rail System, which started to carry passengers before the tests to be carried out in order to serve in line with the public interest, were completed. Muhittin Böcek28 separate tests, which started with the instruction of , have been largely completed. In this context, prototype testing, production testing, post-assembly tests, acceptance tests, system tests, integration and interface work tests, and security tests were successfully carried out. Finally, within the scope of safety tests, 20 tons of sandbags are loaded on the tram cars and the compatibility of the energy transmission line, tram and rails is tested.

bus terminal will carry passengers in August
bus terminal will carry passengers in August

PASSENGER TO BE MOVED IN AUGUST
29 has started to run in the scope of ”test operation V in July, and the test drive will continue uninterrupted until the required operational performance of Varsak-Otogar line is achieved. Following the test drives of the tram, it is planned to start carrying passengers in August.