Mersin Port Grows With Investments

mersin port is growing with investments
mersin port is growing with investments

New investments that will increase the competitiveness of Mersin Port and provide more berthing capacity of 2 mega container ship are continuing.

While being operated by the General Directorate of TCDD, 11 was privatized in the first place in TCDD ports with the 'Transfer of Operating Rights' method on May 2007 for the year 36. Drew attention to new investments in Mersin Port operated by MIP.

400 TURNING ADDITIONAL FIELD WILL BE CREATED
Mersin Chamber of Shipping (MDTO) Deputy Secretary General Halil Delibaş, MIP 2019-2020 period for the creation of additional sites, gate and highway connection road arrangement and terminal operation system (TOS) update has made significant investments.

Delibaş also stated that the CFS site was planned to be taken out of the port during the second phase of MIP's Field Project.

OPTICAL RECOGNITION / READING SYSTEMS WILL BE COMPLETED TO THE YEAR
Within the scope of Optical Recognition and Highway Connection; The consolidation of the doors, direct motorway connection and the optical recognition / reading systems on the docks and gates will be completed next year.
System automatic doors, ease of damage detection, 7,5 million dollar gate and highway
The connection investment includes 1,5 million dollar port area and port connection investments. TOS & GTOS Investments: Updating the container operation system and continuing to develop the CFS & Conventional operation system also requires the 3,5 million dollar investment.

“2 MEGA CONTAINER SHIP WILL BE PROVIDED WITH MORE CAPACITY”
Well; What will EMH2 (East Mediterranean Hub) investment provide? With the completion of the second leg of the 241 million dollar expansion project of Mersin Port, the 2 mega container ship will be provided with more berthing capacity. This project is scheduled to be completed in 2021. The port is still capable of accepting vessels up to 18 thousand TEU. MIP's 500 meter additional berth, 900 thousand TEU additional berthing and field capacity issues are continuing to prepare the pre-construction work, belirtil he said. (Gift Eroğlu - the Mersinhaberc)