Current Situation at Esenboğa Airport

esenboga the last situation in the airport
esenboga the last situation in the airport

Chairman of the Board of Directors and Deputy General Manager Mehmet Ates, the airport executives and the contractor company received information from the officials of the State Airports Authority (DHMI).

Stating that the teams are working intensively for the works to be completed within the planned period, the Pat Fields Repair, Extension and De-Icing Apron Production reached 90 level of%.

Noting that the works within the scope of the project will cost 155.830.522,17 TL, Ateş gave the following information about the completed and ongoing works: ”The construction of the parallel taxiway, which will also be used as a departure runway in the dimensions of 3750x 60 meters (including shoulder), has been completed. assemblies continue.

The Connection Taxiway construction, which will connect the parallel taxiway and the apron located in front of the terminal building, has been completed, and the track lighting armature assemblies continue. 2 De-icing Aprons have been completed. ”