Extending 2 Monthly Period for Trambus in Sanliurfa!

Extending 2 month for sanliurfada trambus is expired
Extending 2 month for sanliurfada trambus is expired

It is known that the cost of 70 million liras will be approximately, and the infrastructure, mast, stall, energy wires for 35 million pounds spent for the trambus project for the month of the additional period of 2 is ending today. Now the public is asking when the trambles will come, or if the money spent on the project goes away.

The 2018 for the 'Trambus Project', which is planned to be implemented in 2 with the promise of a solution to the traffic problem in Şanlıurfa, is ending today.

In the tender contract, 09.06.2017 begins the work on the 08.06.2018 and the end of the trambus project in Sanliurfa is expected to be completed in this round.

Can Hallaç, Deputy Secretary General of Şanlıurfa Metropolitan Municipality, said that the trambus project in the transportation master plan will serve 2 lunar lag due to the economic problems in the country. Approximately 2 million pounds will cost about 70 million pounds of underground projects, the work was spent for the stall and superstructure. The rest was to be paid to the company. However, there is no trambus production for Sanliurfa at the moment, and there is no payment from Iller Bank. Now, the public is asking if the trambus does not come and the question of whether the 35 million liras will go to waste.

2 GOES MONTHLY TIME

After the completion of the construction works of the stops started within the scope of the 1 1st stage located in the historical Hanlar region, Balikligol, Sanliurfa Museum, Divanyolu Street, Cakli passage and Ataturk Boulevard route in Sanliurfa, the time for the 2 month delay of the trampus voyages carried out in the first test flock expires tomorrow. 12 December 2018 2 will be scheduled to start the month with the announcement of the Deputy Mayor of the Metropolitan Municipality M. Can Hallaç, visited the supplier company of the Trambus project, Bozankaya AS. Hallaç, who came together with the authorities of the supplier company to discuss the trambus project in Şanlıurfa, stated that the project was delayed due to the negative developments in the sector. However, the 2 given for the company ends tomorrow in a month. Deputy Secretary General M. Can Hallaç, who made a statement due to the disruption, said: ada We visited our company in Bozankaya, which made our Trambus project. Due to the economic situation throughout the country, our company has been faced with serious problems about Trambus production for a long time. We have been negotiating with the parties for a long time to resolve these problems. We brought all the raw materials to the solution point, all the parts were supplied and they started to manufacture quickly and they would send the trambus to Sanliurfa which will be ready for delivery in 2 months. There is one trambus in Sanliurfa and education is still in progress mevcut.

FARMER 21 LAST 21 NOVEMBER HISTORY

Speaking at the Transportation Summit held in Sanliurfa in November, 21 Sanliurfa Metropolitan Municipality Mayor Nihat Ciftci said, Büyük As the Metropolitan Municipality, we moved from the very important bus fleet to the trambus system. We continue our tests with the 7.5 km trambus route which we started in our historical region. In addition, we started to work on the 34 kilometer rail system. Our projects and tender process have been completed and we are now launching infrastructure works. The higher the quality of transportation, the better the quality of life of people living in that city şehir.

THE PROJECT MAY BE GRANTED OR REMOVED IN NEW MANAGEMENT

31 No one in Şanlıurfa locks in the local elections to be held in March 2019. Candidates whose names are mentioned for the Metropolitan Municipality will either forget the trambus project or revise the project themselves. This means a loss of time and a new cost. Şanlıurfa public opinion, 'the project will not be implemented' prevailing, the race will not be found again in the election race, Mayor of Sanliurfa Metropolitan Mayor Nihat Ciftci retains the silence on this issue. (Hüseyin ÖZKAN - AJANSURF to)

Current Railway Tender Schedule

For 24
For 24

Tender Notice: Level Crossing Guard Service

October 24 @ 14: 00 - 15:00
About Levent Elmastaş
RayHaber editor

Be the first to comment

Comments

This site uses Akismet to reduce spam. Learn how your comment is processed.