Trabzon Light Rail System Project Works Completed

Orhan Fevzi Gümrükçüoğlu, Mayor of Trabzon Metropolitan Municipality, made explanations about light rail and transportation investments.

LIGHT RAIL SYSTEM PROJECT DELIVERED TO OUR MINISTER

Gümrükçüoğlu ”The project works of the light rail system have been concluded. Project works cost 3 million. Under the conditions of that day, it held 3 million. Smaller projects held more in other cities. Light rail system Akyazı reaches Akçaabat Akçaakale from the main station, on the other hand, to the university and the airport. The first part, which will extend from Akyazı to the Square and the Airport, was first delivered to the ministry of ministry. He personally reached the minister. According to our first calculation, the first stage will cost 1 million and 800 million. When our transport ministry accomplishes this, we are willing to pay installments for 1 years. It will be a very good transportation line when it gains the habit of using all citizens of the city. This line will take you to the Akyazi from the airport in 30 minutes. This is a very important step for the traffic of the city to relax. ” said.

130 NEW BUS

130 new buses were launched and a fleet of 172 vehicles was created in order to enable citizens to travel more comfortably and safely in public transportation.

WE OPEN BICYCLE ROAD TO SERVICE

The 5,6 km walkway between Beşirli and Kemerkaya neighborhoods of Ortahisar district attracts great interest. The bike path parallel to the road was also appreciated. Very modern bicycle path

BREAKING THE STORAGE

We are the city with the most road network except the highways network. Path means civilization. In the first 4 years after the metropolitan city, we performed 1 million 300 thousand tons of asphalt service. The history of Trabzon is the biggest record after the Republic. It is the product of labor. 5. 400 thousand tons of asphalt targets in our year target. As of today, we have realized a thousand tons of 300. So 4,5 annually as 1 million 600 thousand tons of asphalt laid. We serve without advertising.

ERDOĞDU ROAD GET INTO SERVICE

The construction of the section between Atapark and Çatak of the Erdoğdu Road was completed and the double lanes were opened in service.

THE LEGISLATIVE BULVARI CONTINUES

Our President of the Republic, Mr. Recep Tayyip Erdogan, gave the biggest and most beautiful response of the 23,7-kilometer Kanuni Boulevard as if it were stopped. The construction of the Law Boulevard continues and completion work continues within 24 months. The Kanuni Boulevard, which is being built as three lanes going and three lanes coming, has 14 bridges, 8 level crossings and 8 double-tube 9 tunnels, will make a significant contribution to transportation when completed.

MULTIPLE PARKING CONSTRUCTION CONTINUES

Located in the south of Yavuz Selim Boulevard, 25 has more than a million total expropriations. 310 parking lot with car park construction will be created. In the determination of our 310 vehicle, it was determined that the input and output traffic at Yavuz Selim Boulevard was only calculated after the calculation of the number of vehicles. We are always behind the ground that I declare that there will be parking for 750 vehicles at the bottom of the Tanjant Bridge.