3 from the Ministry of Transport. Response to Corruption Claims at the Airport

The Ministry of Transport and Infrastructure, the total investment amount 10 billion 247 million Euro 4 stage of the Istanbul New Airport Project, as a result of the revisions, the cost of the contractor in favor of the contractor to pay for the differences in the method determined by the administration, and the public in this case to be damaged or in the case of the contractor firm to make a profit is not in question.

From the ministry, CHP deputy Aykut Erdoğdu'nun, Istanbul New Airport about the allegations of corruption was made.

In the statement, Erdoğdu, ın Istanbul New Airport Project, depending on what the elevations and coordinates changed? Pro, 3 May 2013'da tender specifications and annexes of the procured project, jeans, coordinates and the original master plan can be changed with the approval of the administration was reminded that it was connected. Following the signing of the contract with the company established by the joint venture, the company made detailed geological surveys supported by the university reports on the ground where the airport will be constructed.

The total investment amount 10 billion 247 million 4 stage of the project as a result of the revisions, the cost of the contractor in favor of the contractor can be determined by the method of payment to be determined by the administration, the statement declared by the administration, the public in this case is damaged or the contractor firm to make a profit the situation is not mentioned.

In the case of Erdoğdu, in the case of lar place where delivery of 2 years after the contract has been signed, a situation in favor of the operator and public damage has been created??, In the article titled söz Place Delivery işlet, it is stated that if there are official decisions to be taken as an obstacle to the delivery of land, It transferred.

Istanbul New Airport 19 2013 XNUMX signed after the signing of the contract required to complete work on the completion of the process for the completion of the process can not be completed, the statement pointed out that the delivery of the project, the company to prepare the project, place delivery, on-site map measurement, ground survey and seismic studies were recorded. .

”The banks have provided a total of 4 billion euros in 480 billion“

In relation to Erdoğdu's question esi Is the financing guarantee conditions changed after the tender and if the loan debt is not paid and transferred to the public??, The Build-Operate-Transfer is a non-budget financing model and the entire investment is fully funded by the private sector outside the state budget. The statement stated that the company has to provide self-resources to the minimum 20 of the investment amount and meet the rest through credit.

Under the title of halinde Loan Undertaking in of the Law on the Construction of some Investments and Services within the Framework of Build-Operate-Transfer Model, ler If the facility is taken over by the relevant administrations before the period of investment and services, the said Administration is authorized to undertake the external financing provided for the financing of the investment and services. In this context, the annulment of the application contract for the Istanbul New Airport Project, 36. and the principal and interest expenses in case of termination of the contract by the company due to the company's defect in the period of termination of the contract, in case of termination of the contract, free of charge, ıyla kadar investment in the investment and withdrawal from the loan but not returned to the credit institutions until the date of termination of the contract. , except for the company's defect in case of termination of the main money and all financial expenses, the current loan contract terms and conditions within the administration will be paid to the credit institutions by the administration.

Under the terms of the contract and the relevant articles of the contract, the undertaking's undertaking the debt of the company with the banks concerned and the direct DHMİ General Directorate also participated in the contract negotiations and the parties to the said contracts were recorded.

A total of 4 billion 480 billion by the group of banks formed by the participation of private sector banks such as Vakıfbank, Halk Bank as well as state banks such as Vakıfbank and Halkbank under the leadership of Ziraat Bank for the financing of the Istanbul New Airport Project, one of the biggest investment projects in the history of the Republic. Provided that there is no treasury guarantee in the project made within the scope of Build-Operate-Transfer.

I The land that lost its forest character was rehabilitated “

In response to Erdoğdu's question proje Has the ground, wind values ​​and the environmental impact of this airport been taken into account when selecting the airport? Cev, the area planned for the project is close to the sea and the city center, the cost of expropriation for a project area of ​​this size is quite low and Atatürk Airport It is pointed out that the inability to meet the current capacity is one of the most important elements in the choice of place.

It was emphasized that the location of the airport was previously a mining site and lost its forest character. It was emphasized that the land filled with pits was rehabilitated and transformed into a green space which is very green and environmentally sensitive.

It is stated that detailed pre-tender studies are carried out, environmental impact assessment (EIA) approval is obtained for the project area, wind measurements, ground survey reports are prepared and given to the tenderers. It was noted that the studies on flora and fauna of the region were carried out, birdwatching studies were carried out meticulously and the project was completed, an energy-efficient, environmentally friendly, environmentally friendly, unobstructed, green and Leed Certificate (Leadership in Energy and Environment-Friendly Design) was aimed to be introduced to the country.

In response to Erdoğdu's question, yap Will the airport be inaugurated because IGA cannot build the facilities necessary for THY? Olan, the opening of the Istanbul New Airport will be held in October as planned.

In addition, the problems that can be experienced in this scale and after the move can cause significant problems for all parties and the aviation sector.

In addition, Erdoğdu's question olmadı Are materials used in the construction of the airport removed from other places ve were answered by emphasizing that the use of state-of-the-art systems and devices and the use of disassembled materials was not in question.

Source: www.dhmi.gov.tr

Railway News Search

Be the first to comment

Comments