Irmak Zonguldak Line Km: 368 + 448 Overpass Construction Works Tender Result

Turkish State Railways Company 2. 2018 Company is the only company in the tender for the construction of the Overpass in the Km: 384087 + 3.951.304,71 with the limit of 6.086.510,77 TL and 368 TL with the cost of 448 / 11 TL at the 4.886.876,66 / XNUMX TRL of the Regional Purchase Service Directorate (TCDD). Project Management Industry and Trade Limited Company has won.

Includes Ø 14 - Ø 32 mm Thick Ribbed Steel Supply and Labor (Including Transport) and other works for Tender Reinforced Concrete. The duration of the work is 300 (three hundred) calendar days from the place delivery.