IBB President Uysal Announces Subway Lines to Open This Year

IMM President Mevlüt Uysal stated that the 7 station between Ümraniye-Çekmeköy Metro and Yamanevler-Çekmeköy will be opened at the end of June. Mecidiyekoy-Mahmutbey Metro, Eminonu-Alibeykoy Tramway and Bostanci-Dudullu Metro from Bostanci to IMES 9 station will be opened at the end of the year announced.

Stating that the reason for the consensus with the companies for the continuation of the metro constructions is clear and clear, Mayor Mevlüt Uysal said, “It is aimed to solve the transportation problems of Istanbul with the completion of Istanbul subways much faster. We wanted the subways to be constructed quickly and with a new finance model. We have decided to continue with the contractors of 4 of the subways that are currently being tendered. The reason we decided to continue is because we have promised that the 4 metro lines that started earlier will open at the end of this year. Our understanding here is this; Why should the subway constructions that do not take so long in the world be long in Istanbul? With the signed protocol, we also reached an agreement for the rapid completion of the Göztepe-Ataşehir-Ümraniye Line. ”

Mevlüt Uysal stated that some of the contractors have some justified requests. Bey For example, the project must be approved by the Monuments Board in Eminönü-Alibeyköy Tramway Line. The responsibility for this is in our municipality. When this article is written and not followed, 3 also comes in a month with 5 per month. But 5 can come in the day, Ama he said.

Another thing that the contractors wanted is the expropriation of the rail system lines and the delivery of the site to the contractor as soon as possible. Uysal said, e If our problems are solved, we will make the construction works quickly. Müt We, as IMM, have done the things we have to do on these issues, Biz he said.

Umraniye - Çekmeköy Metro Company, Yamanevler-Çekmeköy between the end of June 7 station that they want to be finished recording Uysal, said:

“Eminönü- Alibeyköy Tram will be completed by the end of the year. Kabataş- We have brought together two separate contractors who build tunnels and electromechanics in the Mahmutbey Metro. Mecidiyeköy-Mahmutbey will be completed by the end of the year. The part of Bostancı-Dudullu Metro, 9 stations from Bostancı to İMES, will be opened at the end of 2018. ”

HOW MUCH IS MORE QUICKLY THAN ISTANBUL

Uysal stated that they lost time in the 3-5 months when they said uz Contractor should hand it over so that they finish the job ik. Ik When we say that we start and finish the electromechanics of the parts where the tunnel is finished, we save time. Therefore, we have contacted the contractors and provided them. Our point is that; How fast, Istanbul and IMM are in profit. How fast, so cheaply. The more slowly, the more costs it increased. When we make a subway 3 year in 7 year, we don't matter how much money we tend to do, it does not matter 30 damage. When we look at the event, accelerating the construction of the metro facilitated our business and Istanbulites won. Ola

METROLS AND JOURNEYS TO BE OPENED

1 station 20 distance from 16 to Üsküdar-Çekmeköy. Uskudar-Yamanevler 10,5 km 9 station opened. It is planned to open 7 station of Ümraniye - Çekmeköy Metro between Yamanevler and Çekmeköy to the end of June. The total journey between Üsküdar and Çekmeköy will take 27 minutes.

2- Kabataş-The first stage of Mahmutbey Metro between 15 stations between Mecidiyeköy and Mahmutbey will open at the end of the year. The journey of 18 kilometers will take 26 minutes. Ongoing Mecidiyeköy-Kabataş 6.5 kilometers. Once completed, the journey will take 5,5 minutes.

3- Eminönü- Alibeyköy Tramway 14 station will be opened at the end of the year. Even the journey to 10.1 kilometers will last 35 minutes.

4 station with 14.3-13-kilometer 9 station will open at the end of the year. Construction of the electromechanical system of the line was started. The 10.2 mileage and journey between Bostanci-IMES will last for 14 minutes. The remaining 4 station of Bostancı-Dudullu Metro will be opened in 2019. When the Bostancı İDO-Dudullu Metro is completed, the total journey time from Bostancı to Dudullu will be 17 minutes, 21 minutes to the last station, Depot station.