IBB President Uysal Announces Subway Lines to Open This Year

IMM President Mevlüt Uysal stated that the 7 station between Ümraniye-Çekmeköy Metro and Yamanevler-Çekmeköy will be opened at the end of June. Mecidiyekoy-Mahmutbey Metro, Eminonu-Alibeykoy Tramway and Bostanci-Dudullu Metro from Bostanci to IMES 9 station will be opened at the end of the year announced.

President Mevlüt Uysal stated that the reason of the consensus with the companies for the continuation of the construction of the Metro is clear and that Mev With the completion of the Istanbul subways much faster, it is aimed to solve the transportation problems of Istanbul. We wanted to make the metros quickly and with the new finance model. At the moment, we decided to sit with the contractors of 4 and continue the business. We decided to continue the decision to open the 4 subway line at the end of this year. Our understanding here is; Why not take such a long time in the world of metro construction in Istanbul? With the signed protocol, we have reached an agreement for the rapid completion of the Göztepe-Ataşehir-Ümraniye Line. İm

Mevlüt Uysal stated that some of the contractors have some justified requests. Bey For example, the project must be approved by the Monuments Board in Eminönü-Alibeyköy Tramway Line. The responsibility for this is in our municipality. When this article is written and not followed, 3 also comes in a month with 5 per month. But 5 can come in the day, Ama he said.

Another thing that the contractors wanted is the expropriation of the rail system lines and the delivery of the site to the contractor as soon as possible. Uysal said, e If our problems are solved, we will make the construction works quickly. Müt We, as IMM, have done the things we have to do on these issues, Biz he said.

Umraniye - Çekmeköy Metro Company, Yamanevler-Çekmeköy between the end of June 7 station that they want to be finished recording Uysal, said:

Ecek Eminönü-Alibeyköy Tram will be completed by the end of the year. In Kabataş-Mahmutbey Metro, we have assembled two contractors who made tunnel and electromechanics. Mecidiyeköy-Mahmutbey will be completed by the end of the year. The part of Bostancı-Dudullu Metro from 9 station Bostancı to İMES will be opened at the end of 2018. Bost

HOW MUCH IS MORE QUICKLY THAN ISTANBUL

Uysal stated that they lost time in the 3-5 months when they said uz Contractor should hand it over so that they finish the job ik. Ik When we say that we start and finish the electromechanics of the parts where the tunnel is finished, we save time. Therefore, we have contacted the contractors and provided them. Our point is that; How fast, Istanbul and IMM are in profit. How fast, so cheaply. The more slowly, the more costs it increased. When we make a subway 3 year in 7 year, we don't matter how much money we tend to do, it does not matter 30 damage. When we look at the event, accelerating the construction of the metro facilitated our business and Istanbulites won. Ola

METROLS AND JOURNEYS TO BE OPENED

1 station 20 distance from 16 to Üsküdar-Çekmeköy. Uskudar-Yamanevler 10,5 km 9 station opened. It is planned to open 7 station of Ümraniye - Çekmeköy Metro between Yamanevler and Çekmeköy to the end of June. The total journey between Üsküdar and Çekmeköy will take 27 minutes.

2-Kabataş-Mahmutbey Metro, the first stage of the 15 station between Mecidiyeköy and Mahmutbey will be opened at the end of the year. Even the journey to 18 kilometers will last 26 minutes. 6.5 kilometers between Mecidiyeköy and Kabataş. The trip will take 5,5 minutes when completed.

3- Eminönü- Alibeyköy Tramway 14 station will be opened at the end of the year. Even the journey to 10.1 kilometers will last 35 minutes.

4 station with 14.3-13-kilometer 9 station will open at the end of the year. Construction of the electromechanical system of the line was started. The 10.2 mileage and journey between Bostanci-IMES will last for 14 minutes. The remaining 4 station of Bostancı-Dudullu Metro will be opened in 2019. When the Bostancı İDO-Dudullu Metro is completed, the total journey time from Bostancı to Dudullu will be 17 minutes, 21 minutes to the last station, Depot station.