5 New Metro Lines to Istanbul: The construction works of 5 new metro lines, whose tender process has been completed in Istanbul, will begin in the coming days.

Mayor Kadir Topbaş, who presented the 2016 Annual Report of the Istanbul Metropolitan Municipality to the Municipal Assembly, announced that the tender process of the new metro line of 5 was completed and construction works would start in the coming days.

SULTANBEYLİ JOINS THE SKY AND RING

Mayor Kadir Topbaş, who gave the good news that the tender processes of 5 new metro lines in Istanbul have been completed and that the construction works will begin in the coming days, said that when they took office, they determined the most important transportation axis in Istanbul as public transportation and subways.

2019 KILOMETER METHOD IN 400

Kadir Topbas, who announced that they will make a new metro line to Istanbul, said: Am At the moment, our 5 subway line has reached the stage of signing the contract. In the near future, we will do the basic discoveries together. 5 kilometer Başakşehir-Kayaşehir Metro, 6 kilometer Bağcılar-Kirazlı-Small pull -Halkalı Metro, Xnumx kilometer Kaynarca-Pendik Tuzla Metro, 12 kilometer Çekmeköy- Taşdelen- Sultanbeyli Metro and 17.8 kilometers Umraniye-Ataşehir-Göztepe Metro. Actually, we were auctioning a line of 13, one of them waiting for an objection. The contracts of this 6 metro line will be signed and will soon be laid. Thus, when we come to the end of 5, we will bring the rail system on Istanbul's 2019 km. İstanbul

ÇEKMEKÖY-SANCAKTEPE-SULTANBEYLİ METRO PROJECT

There will be 14 stations on the Çekmeköy-Sancaktepe-Sultanbeyli Metro line and the line length will be 17,8 km. The journey time between the two ends of the metro line, which will have a capacity of 70 thousand passengers in one direction per hour, will be 27 minutes.

BAŞAKŞEHİR -KAYAŞEHİR METRO PROJECT

There will be 4 stations in Başakşehir - Kayaşehir Metro line and the line length will be 6,20 km. The journey time between the two ends of the metro line, which will have a capacity of 70 thousand passengers in one direction per hour, will be 10 minutes.

BAĞCILAR (KİRAZLI) - KÜÇÜKÇEKMECE (HALKALI) METRO PROJECT

Bagcilar (Cherry) - Kucukcekmece (Turkey)Halkalı) There will be 9 stations on the metro line and the line length will be 9,70 km. The journey time between the two ends of the metro line, which will have a capacity of 70 thousand passengers in one direction per hour, will be 15 minutes.

KAYNARCA-PENDIK-TUZLA METRO PROJECT

Kaynarca-Pendik-Tuzla metro project will have 8 stations and the line length will be 12 km. The journey time between the two ends of the metro line, which will have a capacity of 70 thousand passengers in one direction per hour, will be 18 minutes.

ÜMRANİYE-ATAŞEHİR-GÖZTEPE METRO PROJECT

In Ümraniye-Ataşehir-Göztepe metro project, there will be 11 stations and the line length will be 13 km. The journey time between the two ends of the metro line, which will have a capacity of 70 thousand passengers in one direction per hour, will be 20 minutes.

THE MOST MODERN METROLES OF THE WORLD IS IN ISTANBUL

Mayor Topbaş stated that the new metros have the most advanced technology in the world and said teknolojik We talked about technological structures, we talked about technological systems and we tried to use the most advanced technologies. Üsküdar-Ümraniye-Çekmeköy line to make it safer in terms of unmanned driver. A very advanced technology, the world is now going through it. This will be implemented for the first time in Istanbul, Turkey. Test drives are currently underway. When it is finalized, when the security limits are determined, we will put them into service for the people of Istanbul. We have taken the 45,1 150 kilometers in Istanbul. There are also approximately 180 km metro lines under construction. İn

Topbas; 14,3 kilometers Dudullu- Kayışdağı- İçerenköy- Bostancı Metro. 18 kilometers Mecidiyeköy-Kağıthane- Mahmutbey Metro Line. 6,5 kilometers Mecidiyeköy- Kabataş Subway line. 10,1 kilometers Eminönü- Eyüp- Alibeyköy Metro. He reminded that the construction of a 13 kilometer rail system, including 20 kilometers Ataköy- Basın Ekspres- İkitelli Metro and 99,7 kilometers Üsküdar-Ümraniye- Çekmeköy- Sancaktepe Metro, is ongoing.

Üsküdar-Çekmeköy Metro will open the 9 station between Üsküdar and Yamanevler in May, and 30 will enter the whole line in August. 6,9 km Hospital- Sarıgazi- Taşdelen- Yenidoğan Metro Line. 10,9 Km Çekmeköy-Sancaktepe-Sultanbeyli Metro Line. This line will reach Sabiha Gökçen Airport. In addition, 15 km Sefaköy-Halkalı-Başakşehir Havaray Line and Kayaşehir subways will also be founded. We are building a metro from Ümraniye to Göztepe. One of the metro projects we care about is from İncirli and Göztepe. KadıköyLine to go to. Havaray is an important transportation project for Istanbul transportation. We have a 87 km havaray project. By the end of 2019, the rate of rail systems will reach 28 percent. This is an important figure, so we leave London and Paris behind. Wherever Istanbul needs a density, we tried to put these systems there. 3. There is a metro starting from Gayrettepe, which is made by the Ministry of Transport, from the airport to the city. In addition, we have a metro line that will go from Vezneciler to Arnavutköy and 3. Airport ”.

RAIL SYSTEM LENGTH IN ISTANBUL INCREASED 332 PERCENT

With the construction of the 9 km Bakırköy İDO -Kirazlı Line, 63,5 km Suburban Line Marmaray Surface, 7,4 km Sabiha Gökçen Airport-Kaynarca and 34 km Gayrettepe- 3rd Airport Line, the Ministry of Transport also has a total of 114 Explaining that the construction of the kilometer rail system line has started, Topbaş said, “Everything continues as we planned. We have determined the places where the subway subway will pass. We connected Asia and Europe under the Bosporus with the project of the century Marmaray. With the Haliç Metro Bridge and Aksaray connection, we started the journey in minutes with Istanbul. We started the Kartal-Tavsantepe Expeditions. Kadıköy-Tavşantepe is now 43 minutes. You get on the metro from Pendik and come to this collar with Marmaray. You reach uninterruptedly from Yenikapı, Aksaray, Olympic Stadium, Airport and Sarıyer. We increased the length of the rail system by 332 percent! We increased the subway network, which was 2004 kilometers in 45,1, to 2014 kilometers in 150. Rail systems used 11 thousand people per day in 532 districts. In 2016, this figure increased to 2 million 300 thousand. Our rail system line is 2019 kilometers in 489. 32 million people can travel underground in 7 districts. Our target for the rail system in Istanbul after 2019 is 1000,15 kilometers. ”

 