The terminal building of the Third Airport is about to end

The terminal building of the Third Airport is about to be finished: Less than a year is left to open the first phase of the Istanbul New Airport, which will be the largest in the world when completed. Elevator and escalators were installed in some parts of the terminal building where the 95 of the construction is finished and the facade and roof installation started. . Total physical progress is at the level of 40s,. Said Akcayoglu, senior manager of IGA Airports Construction. This month we expect a significant increase in this figure ”rakam The rough structure of our control tower is over. The number one runway has only its superstructure. We see that this runway is finished by all taxiways as May-June Bu


1 for the inauguration of Istanbul New Airport (Third Airport) started counting from year to year. While the 95 of the terminal building was completed, elevators and escalators were installed in some sections, and the facade and roof installation started.

At the airport where the rough construction of the Air Traffic Control Tower is completed, the number one track is expected to end with all taxi routes as of May-June.

IGA Airports Construction Top Manager (CEO) Yusuf Akçayoğlu, said in a statement on the subject, this year, the winter conditions were recorded more difficult than last year, so that some jobs could not go at the speed they wanted passed.

Akçayoğlu stated that 22 is working because of winter conditions at the airport construction. Kiş This number will increase towards the summer. We will increase the number of employees to one thousand thousand. Çalışan

Akçayoğlu stated that the airport continued its operations all over the terminal building and added, sürdürül We put the walking bands in the place where we first laid the foundation. We're putting in elevators and escalators. We are wearing the windows. Cam

Akçayoğlu stated that they wanted to finish the rough construction of the terminal building as they wanted, and that they have poured concrete in 2,2 million cubic meters so far, and that this figure is very serious.

Akçayoğlu said, as 95 of the terminal building's rough construction is over. Total physical progress is at the level of 40s. Because of the snow and winter conditions, I said we could not progress as we wanted. We expect a very significant increase in this figure since March. Mart

Akçayoğlu emphasized that their aim is to alan close the building completely before the end of the year Hedef.

Akçayoğlu, in some parts of the terminal building, the roof and roof operations began, he said.

”In June we will energize the building permanently“

Akçayoğlu stated that they would energize the building like June and that the New Airport in Istanbul has energy needs of 250 megawatts.

Yusuf Akçayoğlu said, Yusuf This figure is higher than the total amount of energy consumed by many provinces. Our energy center is finished. 3 120 transformer was installed. total 250 megawatt need. Power transmission line is completed by TEIAS. Building as early as June

Click to read the rest of the news