The Yenimahalle-Şentepe Cable Car Line hit the storm this time

The Yenimahalle-Şentepe Cable Car Line was also hit by the storm: Due to the cracks in the ropes, while the flights are stopped, an overseas report is expected for the rope-drawn ropes.

Annual maintenance of the company's authorized Italian 15 the July coup attempt, citing the failing due to send technical teams to Turkey late Yenimahalle-Şentepe Line cable car stopped at this time due to cracks in excess rope after the storm. EGO General Manager Balamir Gundogdu said that they were taking ultrasound of the ropes and they were waiting for the report from abroad, ini 10-15 cannot do more time in the day. H

FIRST REPORT

Oldu In recent days there have been very big strong winds. We have detected two or three cracks in the first layer of the cable car. So we stopped it automatically. We also explained the issue to our president. We brought a company from Erzincan and we took the ultrasound of the cables, his report was intact. However, the accredited institution was sent to the competent institution abroad.

STUDY IN LABORATORY

The images of the ultrasound are sent abroad and are also being examined in the laboratory there. Cable car cables consist of 20 floors. The crack on the first floor doesn't matter and is standard. But we're waiting for the ultrasound report. The ultrasound report is also standard to us. Our fellow citizens will wait for 10-15 days. 10-15 can not do more times in the meantime, we continue our bus services. N

THE CARE PROBLEM WITH THE ITALIAN RESOLVED

General Manager of EGO Balamir Gündoğdu stated that they had a legal dispute with the authorized Italian company, but said: yetkili The ropeway consists of two stages. The contract period of the first stage is over in May. For the second stage, the tender expires in March 2017. Therefore, the company should look until 2017. But the machine is single. Because the engine is on one side, it affects the other side. Cable and system are the same. Faced with a legal problem, the first stage of the maintenance period has ended because the Italian company said I have no responsibility for it. We said that 2017 was all over in March. We've provided the solution. We will do the maintenance contract with the same company. A great main maintenance for the ski lift I'll also do extensive. During the coup attempt, we were unable to get efficiency. Now it will be a general complete care. Şimdi

Previously, the cable car services were stopped due to the late coup attempt by 15 for the Italian firm.