When will the Ankara-Sivas high-speed train line be opened: Transport Minister Ahmet Arslan, Ankara-Sivas YHT line examined the Elmadağ Site. "In the second half of 2018, we will be connecting Ankara-Sivas YHT to Ankara-İstanbul YHT," he said.

Transport, Maritime Affairs and Communications Minister Ahmet Arslan stated that 70 percent progress has been made in infrastructure works in Ankara-Sivas High Speed ​​Train (YHT) project so far, and that the project will be held on October 6, under the tender of electromechanical systems and superstructure between Yerköy and Sivas.
Arslan made inspections at the Ankara-Sivas YHT Line Elmadağ Construction Site.

Arslan, who emphasized that the spirit of the nation was proved to the whole world by spraying the coup attempt thanks to 79 million, said, “Our job is to be on the construction sites. Our job is to show that our country's business continues at the same pace after July 15, when wrong people are in error. We have to work faster than yesterday in our transportation infrastructure projects, which is indispensable for the development, growth and economy of this country, regardless of who treats. used expressions.

Reminding that the railway industry has been neglected for 1950 years after the 50s, Arslan said that they have been trying to develop the railway sector, which has a very long life of investment, with an extraordinary speed for nearly 14 years.

After the Ankara-Eskisehir YHT line in Turkey, Ankara-Konya, Konya, Eskişehir, Ankara and Istanbul, yht of entering the service between Konya and Istanbul Arslan striking exemplary in this regard, he said:

“In the last 10 years in our country, he has spent 50 billion pounds in the railway industry. We have an effort to create the main backbone from Edirne to Kars and connect them to the Mediterranean, Black Sea, south, Syria, Iraq. with each side of the YHT-knit network of our country and all over Turkey to provide access to the railways, especially if you want to provide integrated transport by road and sea ports. We have come a long way at this point. ”

ANKARA-SIVAS 2 WILL FALL

Ankara-Sivas YHT Project with the 250 km speed per hour, double-line, electric, signaled 405 kilometers long about the new railway was built describing Arslan, all self-managed project between the two cities between the 11 hour travel time will be reduced to 2 hours said.

Arslan, pointing out that the work on the infrastructure of the entire route in question is continuing, “We have achieved 7 percent progress in infrastructure works so far in the project we have been awarded in 70 stages. There are a total of 800 thousand 6 meters of 216 viaducts, the largest of which is 4 meters in length, between Elmadağ and Kırıkkale. The projects of the viaducts, which are special in terms of length, foot angle and heights, are also specially designed. For the first time in the world and in our country, a moving formwork system is applied in the construction of viaducts, which are manufactured by crossing 90 meters at a time. In 16 days, all the beams between one or two feet fall out in place. With this system, the work becomes very economical and the same system is required with a lighter material. ” found the assessment.

“WE ARE ON CONSTRUCTION SITES FOR MORE ACCELERATING”

Emphasizing that the application is very important for the Ankara-Sivas YHT to be put into service in 2018, Arslan stated that they were announced for electromechanical systems and superstructure tender between Yerköy-Sivas and the proposals of the construction tender would be received on 6 October.

Arslan, Ankara-Yerköy said this month they will go out for the tender, said:

“In the second half of October, we will tender electromechanical systems with superstructures. Thus, there will be no parts left between Ankara and Sivas that have not been thrown. In the second half of 2018, we will connect Ankara-Sivas YHT to Ankara-İstanbul YHT and we will have done YHTs from Edirne to Kars within the scope of our 2023 targets. We will carry our country to 2023, 2053 and 2071 altogether. By examining the technique in place, we wanted to give the following message to our 79 million people who stand guard in the squares and embrace democracy all over the country. You protect the squares, but we continue our projects, which are indispensable for the development and development of this country, without slowing down. In order to accelerate even more, we are at the construction sites, we are on the road length, we lay the rail, we make an electromechanical system. We want to present all these projects to our people as soon as possible. ”