Samsun Light Rail System 2. Final Situation in Phase Construction: Samsun Metropolitan Municipality Mayor Yusuf Ziya Yilmaz 27 January The first rail-mounted Gar-Tekkekoy light rail system construction continues rapidly.
The construction of the light rail system in Samsun between the university and Tekkeköy is the 2 between Gar and Tekkeköy. Stage construction 10 will be completed in October.

Light rail system construction continues in all segments and manufacturing items according to the schedule. Currently, catenary systems, rail laying systems, transformers, cable channels, storage areas, such as work continues.
Along the 14 km line, all the sections were completed, while the level crossing at the front of the station was completed and the rails between the Tekkeköy and the service stations between the University Gar met.