Kocaeli tram project in July

The original work in the Kocaeli tram project In July: the tram project initiated by the Metropolitan Municipality of Kocaeli in the hope that there will be a solution to the traffic of the city center of Izmit, the works will accelerate after the holiday.
The 14.4 kilometer route, where the 7.2 mileage route will be laid in total, has announced that the 3.4 kilometer section has been completed so far.
OK on 2017
Head of Kocaeli Metropolitan Transportation Department Mustafa Altay, while closely supervising the work, as of today, the end of the project 221 day of the project went according to the program, 2017 Akçaray said in February will be operational. The 3 / 2 of the infrastructure works starting without laying the rails is over. After that, rail laying will move faster. Altay said, m We scrutinize it in order to avoid any problems. She's experiencing trouble. We expect understanding from citizens. Vat
FRONTIER FRONT OF 11 JULY
In the tramway, pits will be excavated at 3 meter depth in order to plant 'Kataner' poles in the places where rail laying is completed; In the last week of July, 250 pieces 'Kataner' pole will be planted on the tram line, then the energy wires will be pulled over. There will be 30 signalized intersection on the line. Bayram next 11 from July on the front and Şahabettin Bilgisu Street infrastructure work will begin.
WE ARE WAITING FOR THE UNDERSTANDING OF CITIZENS
3 / 2 of the infrastructure is completed in the studies starting from the railroad track, the infrastructure of the technical requirements due to natural gas, water electricity, such as the lines of the authorities said,, In order to avoid any problems in the future infrastructure, laying the rail, we think every detail, we scrutinize. Due to the studies, our citizens are experiencing both transportation and disruption of roads and dust-mud problems. Irrigation is done to prevent dust from getting out of working areas. We expect understanding from our citizens who are victims of the study. Çalışma
ADLİYE-ŞAHABETTİN BİLGİSU CADDESİ 11 IN JULY
In the tramway, pits will be excavated at 3 meter depth in order to plant 'Kataner' poles in the places where rail laying is completed; In the last week of July, 250 'Kataner' pole will be erected on the tram line.
After this work is completed, the carrier wires will be energized and 30 signalized intersection will be made on the line. Completion of the rail pavement, asphalt thrown Yahya Kaptan Sarımimoza and Necip Fazil Streets opened to traffic. Bayram next 11 from July on the front and Şahabettin Bilgisu Street infrastructure work will begin.
While the rails were laid, the roads to be used by the vehicles were paved, pavements and intersection arrangements started to be made. Necip Fazıl Caddesi, Gazi Mustafa Kemal Bulvarı and Ankara Street will be closed to traffic as the tramway road is completed and service is entered. In other places the vehicles can pass on the rails.
TRAMVAY WAGONU IN OCTOBER-NOVEMBER
In Bursa Durmazlar 12 tram vehicles, which will be called Akçaray, will come to Izmit in October or November. Meanwhile, Izmit's tram will be exhibited at the fair will be opened in Germany said.