3. Airport Rail System Connection Project Gayrettepe Airport line drilling has been completed

Istanbul 3. Airport Rail System Connection Project Gayrettepe - Airport Line Drilling Works

General Directorate of Infrastructure Investments (AYGM), Istanbul 3. Gayrettepe - Airport line drilling works have been completed.

Authorities, 1. for the line that cut the Gayrettepe-Airport line, the 82 part is completed.

As the soundings of the remaining part should be made within the Hastal Barracks, the permission of the General Staff is expected. With the necessary permission, drilling works have been done and 1. cutting will be completed. 2 of the project. Airport - Halkalı line drilling works have just begun. At this stage 1. Cutting machines are also 2. cut. After the completion of the work of the line and light rail vehicles are expected to arrive at the announcement stage.

As known, Yuksel Project Company, which won the tender and project works of the line with an approximate cost of 14.625.440 TL, was signed on 27 July 2015 on 12.987.330,00 TL. Yüksel Proje has been conducting surveys since August.

About Levent Ozen
Every year, high-speed rail sector, the European leader in the growing Turkey. Investments in railways, which take this speed from high-speed trains, continue to increase. In addition, with the investments made for transportation in the city, the stars of many of our companies making domestic production shine. It is proud that Turkish high-speed tren national train ”production has been started in addition to the companies producing domestic tram, light rail and subway vehicles. We are very happy to be in this proud table.

Be the first to comment

Comments

This site uses Akismet to reduce spam. Learn how your comment is processed.