Kartal-Kaynarca metro line will be put into service in 2016

Kartal-Kaynarca metro line will go into service in 2016:Kadıköy - Works are continuing at Kartal-Kaynarca metro line stations, which are the continuation of Kartal metro line.

The first metro of the Anatolian side, which was put into service by Istanbul Metropolitan Municipality in 2012 Kadıköy - Works continue on the Kartal-Kaynarca metro line, which is the continuation of the Kartal metro line.

LINE LENGTH 26 KILOMETERS WILL BE REMOVED
Concrete was drawn for the rolling rails at the Pendik stop of the metro line, which reached the end of the fine workmanship at the stations. When the metro line is completed, the first metro of the Anatolian Side Kadıköy-Kartal Metro will extend to Kaynarca.

Opened in 2012 with a line length of 21,7 kilometers Kadıköy-Kartal Metro tunnel has 16 passenger stations. When the Kartal-Kaynarca Metro is included in the line, the number of stations will reach 19 and the length of the line will increase to 26,5 kilometers.
KADIKÖY-KAYNARCA 38.5 MINUTES

With the Kartal-Kaynarca metro line, which was tendered on March 6, 2013 and planned to be operational in 2016, Kadıköy-The time between Kanarca will be reduced to 38.5 minutes.

 