Ankara Sivas High Speed ​​Train Project

Ankara Sivas High Speed ​​Train Project What is the Case: With the opening of Ankara-Istanbul and Ankara-Izmir High-Speed ​​Train Lines, it is expected to increase the importance of the high speed train line in this route which will provide the connection between the east and the west of our country.

In 2008, the tender for the construction of the infrastructure between Yerköy and Sivas was initiated and manufacturing activities were started. With the Ankara-Sivas High Speed ​​Line, the existing railway line of 602 km will be at 405 km. Thus, the 12 hour, which will be in Ankara-Sivas 2 hour. Ankara-Istanbul High Speed ​​Train Line will be opened with the opening of the 5 hours between Istanbul and Sivas.

The Ankara-Sivas Line is a total of 405 km.

Between Kayas and Kirikkale:

-Kayaş-Elmadağ (Km 12 + 263-45 + 440): Financial offers were received on 04.09.2015.

-Elmadağ-Kırıkkale (Km 45 + 440-74 + 100): Financial offers were received on 07.09.2015.

-V7-V9-V10-V15 (4) construction work on the viaduct of 05.03.2013: 20 was made on 2014 February XNUMX and Doğuş Construction contract was signed.

V9 Viaduct

The overall progress is% 44,57. The excavation-filling works were completed and the progression of the 26 Ad foundation was% 100. Pile works; 49 pile will be made from the total 124 pile and 124 Pile pile manufacturing is completed and its progress is% 100. 26 Ad foundation concrete has been poured and the progression is% 100. In column works, 223,43 m column production is completed and its progression is% 41,24.

V15 Viaduct

The overall progress is% 30,08. The excavation-filling works were completed and the progress of the 22 Ad foundation was% 95,65. Pile works; 262 pile will be made from the total 315 pile and 255 Pile pile manufacturing is completed and its progress is% 80,95. 16 Ad foundation concrete has been poured in the foundation and edgepour works and its progression is% 69,57. 56,29 m column production has been completed and the progression is% 7,01.

Progress Between Kayaş and Kırıkkale (%)

INFRASTRUCTURE (23,39)
UPPER (0)
ELECTRIFICATION (0)
SIGNAL TELECOM (0)

Kırıkkale –Yerköy:

• 07.01.2013 signed a contract with Cengiz-Limak-Mapa-Kolin business partnership.

• Place delivery on 21.01.2013

• Total 17,1 million m3 excavation, 5,5 million m3 filling.

• Production of Viaduct-315 with 1 meter length has been completed. Pile, foundation and elevation of VK-2 and VK-4 Viaducts continue.

• In total, 3.846,00 meters tunnel was excavated and 2313 meters tunnel coating concrete production was completed. T-1, T-2, T-3, T-5 and T-6 tunnels have been completed. The excavation support works of the T-4 tunnel continue. T-7 tunnel cladding works continue.

• Production of 47 pieces underpass, 108 culverts have been completed.

• 6 Overpass Production is completed. 5 bridge construction is completed.

• Within the scope of infrastructure works, telecom, electricity, sewage drinking water and botas displacements are carried out at various kilometers.

• The 74 meter-long opening / closing structure in Km: 170 + 240 is completed.

Progress Between Kırıkkale and Yerköy (%)

INFRASTRUCTURE (80,4)
UPPER (0)
ELECTRIFICATION (0)
SIGNAL TELECOM (0)

Between Yerköy and Sivas:

On the 144-174 (282-600 + 398 km to 433-500 + 09.02.2015 km) works have been completed.

Progress Between Yerköy and Sivas (%) (Km: 174 + 000-282 + 600 with 398 + 000-433 + 500)

INFRASTRUCTURE (100)
UPPER (0)
ELECTRIFICATION (0)
SIGNAL TELECOM (0)

-Yerköy-Sivas Infrastructure Supply Works - Section1 (Km: 282 + 600-332 + 300): Tunnel productions, art structure and earthworks continue and 80% physical progress has been achieved.

Between Yerköy and Sivas (%) (Slaughter-1)

INFRASTRUCTURE (80)
UPPER (0)
ELECTRIFICATION (0)
SIGNAL TELECOM (0)

-Yerköy-Sivas Infrastructure Supply Works - Section2 (Km: 332 + 300-363 + 527) art structure and earthworks continue and 15% physical progress has been achieved.

Between Yerköy and Sivas (%) (Slaughter-2)

INFRASTRUCTURE (15)
UPPER (0)
ELECTRIFICATION (0)
SIGNAL TELECOM (0)

-Yerköy-Sivas Infrastructure Supply Works - Section3 (Km: 433 + 500-461 + 000): Tunnel productions, art structure and earthworks continue and 49,9% physical progress has been achieved.

Between Yerköy and Sivas (%) (Slaughter-3)

INFRASTRUCTURE (49,9)
UPPER (0)
ELECTRIFICATION (0)
SIGNAL TELECOM (0)