4 million dollars spent per day for Istanbul-Izmir Highway project

4 million dollars are spent per day for the Istanbul-Izmir Motorway project: The Istanbul-Izmir Motorway project, which is expected to cost about 4 million dollars per day, is continuing at full speed.
Veysel Eroğlu, Minister of Forestry and Water Affairs, examined the Belkahve Tunnel under construction within the scope of the Istanbul-Izmir Highway Project. Indicating that approximately 3 percent of the work in two tunnels with a total length of 210 thousand 85 meters is finished, Eroğlu said, “It is our government that will solve the traffic of Izmir.”
Noting that the project is among the few works of the world, Eroğlu said, “It is a truly wonderful project. An average of $ 8 billion project. 40 percent of the total project is over. In some segments, the completion rate increased to 78 percent. Expropriation is at the level of 91 percent. It was addressed with 28 thousand people. I hope he will reach İzmir in a very short time. ”
FINALIZED IN TUBES
Stating that one of the tubes in the Belkahve Tunnel will end at the end of August and the other in September, Minister Eroğlu said: “We spend 1 million liras a day for Izmir and 4 million dollars a day for the overall project. It will relieve the traffic in Izmir tremendously. ”
THE LONG SECOND BRIDGE
Within the scope of the project, a 3-kilometer suspension bridge is being built from Dilovası to Herzegovina. When completed, the second longest suspension bridge bridge after the Akashi Bridge in Japan will be in Turkey. The total length of the bridge is 3 thousand meters.
NO PROJECT
A total of 18 kilometers 30 viaducts, 7.5 4 kilometers tunnels and 29 bridges will be built. The project will be the largest project in the history of the republic with the BOT model at once. It will be possible to reach Bursa in a maximum of 1 hour, İzmir in 3-3.5, and Eskişehir in 2.5 hours.