The 3th deck in the 5rd Bridge has also been placed

  1. The 5th deck was also placed on the bridge: 3. The 5th deck of the Yavuz Sultan Selim Bridge, also known as the bridge, was also installed. Works are continuing in the 3rd Bosphorus Bridge and the Northern Marmara Motorway Project, implemented by the IC.
    ASSEMBLY OF 5 OF THE TABLES ARE COMPLETED
    The process of putting and assembling the steel deck continues, 5 of the decks are completed. 3. According to the information received from the bridge authorities; there are 59 steel floors in total. The height of the steel decks is 5.5 meters.
    2 units on the European side and 1 pieces on the Asian side were completed. Resources were also made.
    IN THE CONSTRUCTION AREA WITH THE SEA
    New steel decks were brought to the construction site by sea first. Landed by a giant floating crane with a carrying capacity of 1.800 tons. First of all, on the Asian Side, a deck with a weight of 940 tons, a length of 24 meters and a width of 59 meters was placed.
    Finally, the steel deck, which we call the E02 with the same features on the European Side, was replaced. In other words, the placement and assembly of a total of 5 steel decks was successfully completed.
    NIGHT-DAY 1500 PERSON WORKING
    For the construction of 59 steel decks, 1500 people work day and night at a total of three factory sites. Steel sheets coming from South Korea are made ready for panel production in the factory in Izmit Gebze, and then panel production is started at the factory in Tuzla, Istanbul.
    THE WIDE BRIDGE OF THE WORLD WILL BE
    After the production of the panels, they are shipped to Yalova Altınova to form steel decks. The 3rd Bosphorus Bridge will be the world's largest bridge, with its record-breaking 1408-meter main span, which includes both the rail system and the road connection with 4 departures and 4 arrivals.