Ankara-Bursa High Speed ​​Train Project is at a standstill

Ankara-Bursa High Speed ​​Train project is at a standstill: CHP Bursa Deputy and Party Assembly Member (PM) Sena Kaleli stated that in the high-speed train project, the foundations of which were laid in 2012 and will be completed in 4 years, the Bursa - Yenişehir phase is over before the completion of the allocation, about the Yenişehir - Bilecik stage he said that no work has been done.

Noting the inadequacy of the annual allowance allocated for the high-speed train, Kaleli emphasized that the project had come to a standstill and was driven to uncertainty.

Stating that this situation is also included in the report of the Court of Accounts, Kaleli said, “The foundation of the 2,5-kilometer first stage tender between Bursa and Yenişehir of the“ High Speed ​​Train ”project, which will reduce the distance between Ankara and Bursa to 75 hours, was laid on December 23, 2012. During the groundbreaking ceremony held in Balat, it was announced that the project will be completed in 4 years and the first passenger will be transported in 2016, while it was stated that the work on the Yenişehir - Bilecik stage is ongoing. In line with this goal, the construction started excitedly. Routes were changed due to the difficulties of geography, land structure, wetlands and agricultural lands. Tunnels increased, costs increased. As a result, it was revealed that the Bursa - Yenişehir stage could not be completed with the tender conditions. The project budget of 393 million 170 thousand liras was finished before the tunnels were completed. Uncertainty about the Yenişehir - Bilecik stage, which is another pillar of the project, continues. On the other hand, according to the information we learned from the Ministry, the allocation for the project in 2014 is 120 million TL. The amount spent so far from the appropriation allocated for this year is 75 million TL. Considering the investment program of the SPO, the total amount of the project is 1 billion 72 million TL, it is almost impossible to reach 2017, which is included in the investment program of the high-speed train ”.

"The Court of Accounts Requests All Aspects of the Project to be Drafted and Investigated if Required"

Stating that the high-speed train project, which will reduce the distance between Ankara and Bursa to 2.5 hours, has also been included in the reports of the Court of Accounts, Kaleli explained that the following statements are included in the report:

“At an approximate cost of 870 million TL, the final project was tendered and the contract was signed for 393,2 million TL, and after the tender, the 75 km of the 50 km long line. It has been observed that a high rate of physical realizations have been achieved in the work items that are determined to give a higher unit price compared to the approximate costs during the implementation of the contract, where the route change is made in the first section and the line width is increased, and the tunnel floors in the sections where the line change is not made, TCDD General Directorate has all aspects of the works and transactions related to the project, tendering and manufacturing process related to the Bursa-Yenişehir section railway infrastructure construction work, which cannot be completed within the cost, and if necessary investigated. "

On the other hand, the CHP Bursa deputy Sena Kaleli, who also brought the issue to the agenda of the Parliament, prepared a motion by request of the Minister of Transport, Maritime Affairs and Communications, Lütfi Elvan.

The statement includes the following statements:

The foundation of the 2,5-kilometer first stage tender between Bursa and Yenişehir of the “High Speed ​​Train” project, which will reduce the distance between Ankara and Bursa to 75 hours, was laid on December 23, 2012. During the groundbreaking ceremony held in Balat, it was announced that the project will be completed in 4 years and the first passenger will be transported in 2016, while it was stated that the work on the Yenişehir - Bilecik stage is ongoing. In line with this goal, construction started excitedly. Routes were changed due to the difficulties of geography, land structure, wetlands and agricultural lands. Tunnels increased, costs increased. As a result, it was revealed that the Bursa - Yenişehir stage could not be completed with the tender conditions. The project budget of 393 million 170 thousand liras was finished before the tunnels were completed. On the other hand, uncertainty about the Yenişehir - Bilecik stage, which is another leg of the project, continues. In this context;

  1. At what stage is the work in the Bursa - Yenişehir and Yenişehir - Bilecik stages of the high-speed train project that has been started between Ankara and Bursa? Will there be any deviation from the goal of moving the first passenger in 2012, which was announced when the foundation was laid in 2016?
  2. Despite the fact that the budget of 393 million 170 thousand liras signed by TCDD with the contractor consortium for the Bursa - Yenişehir stage was completed before the tunnels were completed, what percentage of the stage was completed with this money?
  3. Will there be a new tender for the Bursa - Yenişehir stage? If so, how does the calendar for the tender process work? What studies are carried out in your Ministry regarding the process and the outcome of the project?
  4. What work has been done for the Yenişehir - Bilecik phase, which is the other leg of the project? At what stage are the works related to the stage still?

  5. Considering that the total amount of the project in the investment program of the SPO is 1 billion 72 million TL, the expenditures made so far 393 million TL and the appropriation for 2014 is 120 million TL, how many times the extension of time is considered for the project? When will the first passenger be transported by high speed train between Ankara and Bursa?

  6. When designing the Ankara - Bursa high-speed train line, is the responsibility of both the cost-increasing factors and the situation and uncertainty about the 2016 target under the administration or the contractor consortium? How much will this affect the budget of the project?

  7. To what extent have TCDD General Directorate taken into account the evaluations of the Court of Accounts that "TCDD General Directorate has all aspects of the works and transactions related to the project, tender and manufacturing process related to the railway infrastructure construction of the Bursa - Yenişehir section to be examined and if necessary investigated"? Has a study been initiated on this subject?

  8. How many occupational accidents occurred during the construction of the Ankara - Bursa high speed train project? How many people are killed, injured and disabled in these occupational accidents? Has there been a restriction on the allowances reserved for occupational safety and security due to the cost increasing factors arising during the construction of the project?