Gebze-Orhangazi-İzmir Highway Project

Gebze-Orhangazi-İzmir Highway Project: Expropriation and construction works are continuing rapidly in the Gebze-Orhangazi-İzmir Highway Project, which will reduce the transportation between Istanbul and Izmir to 3,5 hours.
The General Directorate of Highways announced that Izmit Bay Bridge Bridge, which will be opened next year, will complete the excavation works in the northern and southern anchorage areas.
The construction of tower basin foundations is completed, 16 meter diameter and 27 meter high steel shafts placed on the base of the caisson foundation 42 meters indicated that the 40 meter depth of the basin in the area of ​​the baselines of the excavations were done in the base area for ground improvement 2 meter diameter and 34,25 meters 195 steel piles on the neck were recorded.
In the statement, it was emphasized that the production of anchorage base and tie beam suspension bridge tower, deck and main cable steel in the tower foundations continued in accordance with the program, the excavation was completed in the Samanlı Tunnel and the level of 72 percent was reached in the tunnel arch concrete works, and the piling works in the Selçukgazi Tunnel were completed, It was stated that the work started, the excavation continued in 2 mirrors in the entrance and exit areas of the Belkahve Tunnel and 720 meters progress was made.
In the statement, 253 meter-length north approach viaduct header beam production studies and a thousand 380 meter-long southern approach viaduct elevation and deck installation studies are continuing, stating that the 12 in Gebze-Bursa and Xnumx in the Kemalpasa-Izmir section of the work in the 2 viaduct was progressing rapidly.
Gebze-Orhangazi-Bursa and Kemalpaşa-Izmir section of the earthworks, large and small art structures manufacturing, grounding work is rapidly progressing in the statement, the project's construction process determined as 7 years, 2015 end of the Gulf Bridge Suspension Bridge, Gebze-Gemlik and Kemalpaşa - It was emphasized that the completion of the works in Ýzmir section was aimed.
- 4,5 billion lira was spent on the project
In the statement, in the regions of Gebze-Orhangazi-Bursa and Kemalpasa-Izmir in the expropriation 82, 32 physical realization in the construction work is provided by the information given, the 1,5 billion-dollar work done by the company, the General Directorate of Highways, expropriation work 1,31 billion pounds spent, as of today 4,5 billion TL lira spending was recorded.
In the statement, where 405 thousand 4 personnel, 579 of which are technical personnel, and 85 construction machines work in the project, the Izmit Bay Crossing Bridge is the 4th suspension bridge with the world's largest middle span, 384 kilometers of highway between Istanbul and Izmir and It was reported that 49 kilometers of road will be built, including 433 kilometers of connection roads.