The Decision of the Limestone Quarry to Stop the Execution of the EIA Report

Decisions of Limestone Quarry to Stop the Execution of EIA Report: Kocaeli 1. The Administrative Court stopped the execution of the EIA report for the limestone quarry and crushing and screening plant, which is planned to be established in Kartepe district of Kocaeli in order to supply the high speed train line (YHT).
Kartepe Tourism Association officials in Maşukiye planned to be operated by the General Directorate of TCDD limestone quarry and crushing and screening facilities to the Ministry of Environment and Urbanization on the grounds that the decision of the decision against the Ministry of Environment and Urbanization was decided to stop the execution.
The court decided to stop the execution due to the lack of proper meeting with the participation of the public, the measures to be taken during the operation of the plant to eliminate the negative effects of the dust and particles on the agricultural lands and the natural trout in Yanık Creek and the reservations were not abolished.
President Ahmet Cüneyt Yilmaz, the resolution of the dispute requires technical knowledge and expertise to stop the execution of the decision to discontinue the decision to discontinue the executive with the thought that the decision to discontinue the executive said that the decision to stop the execution.

About Levent Ozen
Every year, high-speed rail sector, the European leader in the growing Turkey. Investments in railways, which take this speed from high-speed trains, continue to increase. In addition, with the investments made for transportation in the city, the stars of many of our companies making domestic production shine. It is proud that Turkish high-speed tren national train ”production has been started in addition to the companies producing domestic tram, light rail and subway vehicles. We are very happy to be in this proud table.

Be the first to comment

Comments

This site uses Akismet to reduce spam. Learn how your comment is processed.