Daily follow up to YHT line Ya Estram

Daily follow up to YHT line Ya Estram
While YHT line works are progressing at full speed, the works are constantly checked by the authorized and the beginning of the work. However, the situation is the opposite in Eskişehir. Estram studies are going halfway, and the authorities do not even give information to the citizen, let them inspect on site, let alone check. When a citizen wants to convey a shortage, only one authority does not respond positively or negatively! ..

"We are continuing our work schedule with no serious construction work on the Ankara-Istanbul-Ankara High Speed ​​Train line until September 30," said Binali Yildirim, Minister of Transport, Maritime Affairs and Communications.

Yıldırım came to the Osmaneli district of Bilecik by helicopter to investigate the construction of the Ankara-Istanbul YHT line. Yıldırım noted that after the briefing he received from the contractors of the contractor company, they completed one of their monthly meetings at the construction site of the 154-kilometer section of the Ankara-Istanbul YHT project from Eskişehir İnönü to Köseköy.

According to the work program, monthly meetings to determine whether the work has been carried out onsite, if there is a glitch, take the necessary measures to ensure that the project ends without delay, stating that the Lightning, said:

“What is the situation we are getting now? The entire line is 154 kilometers. The tunnel amount is 35 kilometers, the viaduct amount is 10 kilometers, and the other parts are split and fill. The infrastructure of the line has been completed by 99 percent. Panel works have been completed in approximately 100 kilometers of the line. In other words, the rail laying process has been completed and the remaining works continue. 6 thousand 2 poles were installed from a total of 100 thousand poles. Channel work on signalization has been completed to a large extent. The shooting of signal cables has also started. In short, the project continues as planned. Although there are some delays, these delays will not have any negative impact on the overall completion and completion of the project. They take the necessary precautions for him.

”NIGHT DAY WORKING“

Stating that the line is important and not only connects Ankara to Eskişehir, Bilecik, Sakarya, Kocaeli, Istanbul, Yıldırım continued his words as follows: We can include the fact that it is vital that the line is completed and commissioned as soon as it has a very serious population area since a large part of it is realized.

For this, our friends work day and night. DDY General Directorate continues the project with a daily follow-up as a team. Our aim is to complete the project in a short time and start the trips until a year later. You know, we will be ready by September 30, but the opening of the project will depend on a day to be decided after. But until 30 September, we continue our work schedule without any construction work related to a serious project. ”

Regarding estram works, the patriots saw the Metropolitan Mayor Yılmaz Büyükerşen only at the memorial stone ceremony. After that, the president did not even come and supervise the work. Seeing the head of the citizen walking around in the work area is waiting for the moment to express the problems.

Source : I www.eskisehirgundem.co