When will the test run on the Marmaray line start?

When will the test run on the Marmaray line start?
Rough construction of the 13.6 km Bosphorus tube was completed. 27.2 km of 24.6 km length of rail installation was done.
The final project in the Marmaray project of the century. The construction of the Gebze-Throat tube was started at 2004.Halkalı 76 km in total with the route Marmaray, the last situation months before the opening:
On the 13.6 km route between Ayrılıkçeşme and Kazlıçeşme, all the rough construction, except for the Sirkeci station area, is completed, while the architectural and electro-mechanical works continue. Temporary rail installation was completed except for Kazlıçeşme and Ayrılıkçeşme station regions. Starting from the Anatolian side, the catenary began to be laid. 13.6 km section of the Bosphorus crossing rail mounting rails km of the 27,2 24.6 km long, of 16.6 km of rail concrete was completed.
100 month has passed
The 2012 by the end of the year 100 in the throat tube pass, 7 per month, 700 per thousand 32 per month worked for the tube transition, while XNUMX lagged behind the end of the year. Gebze Haydarpaşa, Sirkeci-Halkalı The last 1 per month for the improvement of suburban lines worked 350 thousand hours per month 90, for the job of the month of the month worked for 100 million 2 thousand hours of 800 people.
In Sirkeci Station, which is one of the important steps of the project, the excavation progress reached to 85 and the rough construction progress reached to 45. In the 20 km section of Gebze-Pendik, cable, signal, kataner, traverse and ballast removal works are completed. Design work for 11 station, 63 art structure and line length route in this section has been realized to a great extent. In addition to the 400 bin m3 line excavation between Gebze and Pendik, 100 bin m3 excavation and 12 thousand cubic meter filling at the Gebze depot area in addition to the 3 bin m60 line filling, Halkalı 100 bin m3 excavation and 40 bin m3 preloading were completed at the warehouse. 29 October 2013 will be opened in May, the test drive of the Bosphorus tube test planned to be opened. Production of 440 units from 355 pieces railway vehicles to be provided for Marmaray was completed and stored in Haydarpaşa and Edirnekapı gare areas.

Source : I www.patronlardunyasi.co

About Levent Ozen
Every year, high-speed rail sector, the European leader in the growing Turkey. Investments in railways, which take this speed from high-speed trains, continue to increase. In addition, with the investments made for transportation in the city, the stars of many of our companies making domestic production shine. It is proud that Turkish high-speed tren national train ”production has been started in addition to the companies producing domestic tram, light rail and subway vehicles. We are very happy to be in this proud table.

Be the first to comment

Comments

This site uses Akismet to reduce spam. Learn how your comment is processed.