CR2 Contract (Railway Vehicle Production)

Marmaray Project, Gebze-Haydarpaşa, Sirkeci-Halkalı Improvement of Suburban Lines: Procurement of Railway Vehicles (Contract CR 2) Tender was submitted to the Prequalification Tender on 07 June 2007 and the Prequalification files were received on 30 July 2007. Examination of prequalification files has been completed on 30 September 2007; 12 On March 2008, bids were received from tenderers. The proposals include financial and technical offer envelopes. CR2 Contract 10 was signed on November 2008 and 25 was launched on December 2008.

Tender Date (Pre-Qualification / Technical Bid Envelope Opening) March 12, 2008
Signing of the contract 10 Nov 2008
Date of start December 25 2008
Completion of Works 1981 days
Original Completion Date (440 vehicle delivery) May 29 2014
Total Contract Price 585.038.104 Euros

Source : www.ubak.gov.t is